DDR Phase 2 Status. EPIM RUF meeting June 16th 2009. DDR XSD. PCA RDS. NPD/PSA Fact database. Daily Drilling reports XML. Daily Drilling reports XML. Daily Drilling reports XML. pdf. pdf. pdf. DDR to regulators and license partners - Scope and deliverables of DDR phase 2. Operators.

Download Presentation

DDR Phase 2 Status

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Ddr phase 2 status

DDR Phase 2 Status

EPIM RUF meeting June 16th 2009


Ddr to regulators and license partners scope and deliverables of ddr phase 2

DDR XSD

PCA RDS

NPD/PSA

Fact database

Daily Drilling reports

XML

Daily Drilling reports

XML

Daily Drilling reports

XML

pdf

pdf

pdf

DDR to regulators and license partners- Scope and deliverables of DDR phase 2

Operators

Regulators

PSA/NPD

app

Drilling

App/DB

Drilling

data

License Partners

LicenseWeb

Drilling

App/DB

Schema/Business validation


Status

Status

  • As of March 24th EPIM officially owns the DDR XML schema

  • Partner reporting in License web

    • Same information content as submitted to PSA

      Status:

    • Specification document completed

    • Build - in progress

  • Updates to XML schema – documented in separate document

    • WITSML 1.4.0 compliance

    • Correction of misspelling of enumerated values

    • Correct use of wrong data types (For example on comments which are limited to 256 characters)

    • Some elements may be changed from ‘optional’ to ‘mandatory’ in the report.

    • SAWSDL annotation

    • Coordination with Energistics

      Status:

    • Tested and completed – ready for approval by project group


Status1

Status

  • Standard report layout for PDF reports

    Status:

    • Completed – approved by project group in meeting February 9th 2009

  • User guide updates - PSA

    Status:

    • Draft version available at(http://www.ptil.no/getfile.php/PDF/DDRS%20-%20borerapportering/WITSML_drillReport_profiled_schema_for_usermanual.xml)

  • Schema validation error messages - PSA

    Status:

    • Business rule validation error messages will be updated by cut of to new formats


Way forward

Way forward

  • Completion of DDR partner reporting in LW – Responsible Tieto, follow up by LW User forum

  • Communication to EPIM members regarding new DDR formats and date for go live of DDR reporting in Licenseweb – responsible EPIM Report User Forum – Drilling

  • Communicate to operators regarding cut of date for new formats to PSA – Responsible PSA

  • Project documentation will be added to EPIM’s document repository

  • October 1st is the date when PSA will require DDR according to the new formats, and the new DDR partner reporting solution in Licenseweb will be ready for use!

  • Further improvements and extensions of the DDR XML schema will be handled by EPIM RUF – Drilling

    • A possible first case can be increased information scope in DDR. See Next slide


Additional information requirements nb not included project scope

Additional information requirements – NB not included project scope

Identified during DDR Phase 1

  • Operation codes

  • Cement

  • Period of operation

  • “Drilling like units of measure”

  • Formation name – selection list

  • Datum (reference points)

  • Casing type

  • Pressurized coring

  • Well stimulation (At well testing) indicator

  • Perforation - Shot density

  • RIGTYPE

  • Bit data

  • Side track

  • Tight wells

Identified during DDR Phase 2

  • Cost

  • Report nr -> A sequence number. Each day of operation is a new number increment

  • Start date -> Start of reporting/operation

  • Water depth

  • Bit record (additional info): grading, depth in, depth out, drill lenght (m), duration (hr), rop (m/hr)

  • Casing (new section): OD (in),top, bottom, weight, grade, estimated top of cement

  • "Duration" should be included for all time intervals.