On the Benefits of Planning and Grouping Software Maintenance Requests

On the Benefits of Planning and Grouping Software Maintenance Requests. Gladston Aparecido Junio (PUC Minas , Brazil ) Marcelo Malta (PUC Minas , Brazil ) Humberto Mossri (PUC Minas , Brazil ) Humberto Marques-Neto (PUC Minas , Brazil ) Marco Tulio Valente (UFMG , Brazil ).

arlene
Download Presentation

On the Benefits of Planning and Grouping Software Maintenance Requests

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. On the Benefits of Planning and Grouping Software Maintenance Requests Gladston Aparecido Junio (PUC Minas,Brazil) Marcelo Malta (PUC Minas, Brazil) Humberto Mossri (PUC Minas, Brazil) Humberto Marques-Neto (PUC Minas, Brazil) Marco Tulio Valente (UFMG, Brazil) CSMR – Oldenburg, Germany, March 2011

  2. Motivation • Policies for scheduling maintenance requests: • Continuous: requests implemented as quick as possible • Periodic: requests packaged in larger projects • In theory, the benefits of periodic policies are widely known • Several statistical models have been proposed • Example: Banker et. al (+30% of cost reduction) • Do such gains happen in real organizations? • Theoretical models have not been validated by field studies

  3. In this Talk • Define a simple process – called PASM – for handling maintenance requests as projects • PASM: Process for Grouping Maintenance Requests • Propose a methodology to evaluate maintenance policies • Evaluate the gains achieved by the PASM process in a real software development organization

  4. PASM • Three phases: • Registration • Grouping • Processing

  5. 1st Phase: Registration • Pre-defined time frame for registration • Typicalrequests are buffered • Users can specify that a request is urgent • Ifratifiedbytheprocess manager: • Requestgoesdirectlytoimplementation • No waiting-costs

  6. 2nd Phase: Grouping • No rigid guidelines for grouping • Two forces: size and cohesion • Size: • Compatible with the production capacity • Should not imply in waiting costs that users will not tolerate • Cohesion: • Requests of a project should be functionally coherent

  7. 3rd Phase: Processing • PASM does not fix a development method

  8. Characterization Methodoly

  9. Characterization Methodology • How to evaluate the gains achieved by PASM in a real setting? • Adapted a methodology proposed to understand the behavior of web users • Central idea: Software Maintenance Request Model Graph • Nodes: states of each request • Edges: transition between such states

  10. Software Maintenance Request Model Graph

  11. Metrics • QueueTime = WaitTime + ServiceTime • Service Time = PlanningTime + AnalysisTime + ImplementationTime + ValidationTime + DeploymentTime

  12. Methodology • Classifytherequests in thefollowinggroups: • Before PASM, Urgent • Before PASM, Project • After PASM, Urgent • After PASM, Project • For eachrequest in eachofthepreviousgroups • Generatethe SMRMG • Generate a vector withthepreviousmetrics • For thevectors in eachgroup • Apply a clusteringalgorithm (k-means)

  13. Goal with Clustering • Discover the characteristics of the typicalprojects • Before PASM • After PASM • Evaluate the positive and negative effects of the PASM adoption on such projects • Discover the characteristics of typicalurgentrequests • Before PASM • After PASM • Evaluate the positive and negative effects of the PASM adoption on such requests

  14. Evaluation • We have evaluated the PASM process at DATAPUC • DATAPUC: IT Department of PUC Minas • 34 developers • 40 systems, 4 MLOC • Until October 2008: • (most) maintenance requests handled on demand, in a continuous way. • Starting on November 2008: • DATAPUC has moved to the PASM process

  15. PASM @ DATAPUC • Registering Phase: first 10 days of each month • Grouping: next 20 days • Requests are evaluated and grouped in projects • Cycle is repeated in the next month

  16. Data Source • Same sequence of months: • Before PASM: February-October 2008 • After PASM: February-October 2009

  17. Results: Maintenance Projects

  18. Maintenance Projects: Clusters • QueueTime: + 32% • ValidationTime: +139% • ValidationTime / ServiceTime • 2008: 22% • 2009: 43% • ImplementationTime: - 32% • ImplementationTime / ServiceTime • 2008: 43% • 2009: 23% • AnalysisTime: +54% • AnalysisTime / ServiceTime: • 2008: 18% • 2009: 22%

  19. Maintenance Projects: SMRMG + Probabilities

  20. Maintenance Projects: Summary • More projects: • Before PASM: 22 projects • After PASM: 62 projects • Dominant development task: • Before PASM: implementation (43%) • After PASM: validation (43%)

  21. Results: Urgent Requests

  22. Urgent Requests: SMRMG

  23. Typical Urgent Requests • ImplementationTime / ServiceTime • 2008: 50% • 2009: 41% • QueueTime: - 4 hours

  24. Complex, Error-Prone, Urgent Request • ValidationTime / ServiceTime: • 2008: 48% • 2009: 59%

  25. Urgent Requests: Summary • QueueTime, after PASM: • Typical requests: - 4 hours • Complex requests: + 1 hour (more time to validation)

  26. Conclusions

  27. Contributions • PASM: Process for grouping maintenance requests • Lightweighted process • Three phases: registration, grouping, processing • Methodology to evaluate maintenance policies, based on: • Software Maintenance Request Model Graph • Clustering techniques • Classical queue model metrics • Field study to evaluate the benefits achieved by PASM

  28. Benefits • More requests handled as projects • Side-effects: • More time dedicated to analysis and validation • Less time dedicated to implementation • Urgent maintenance requests: • Handled in less time 28

  29. Further Work • Promote and evaluate the PASM’s adoption by other organizations • Assess the internal and external quality of the software released under PASM guidelines 29

  30. Thank you! My-email: mtov@dcc.ufmg.br