Data Communications Program. DCL Trials DCIT Update MEM ATCT. To: DCIT Plenary From: Matt Maki Date: 07.12.2012. Agenda. DTAP Development Status: DTAP Development/Milestone Deliveries and TIM/CHI Workshops Trials Test/OT&E Timeline

arista
Download Presentation

Data Communications Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Data Communications Program DCL Trials DCIT Update MEM ATCT To: DCIT Plenary From: Matt Maki Date: 07.12.2012

  2. Agenda • DTAP Development Status: • DTAP Development/Milestone Deliveries and TIM/CHI Workshops • Trials Test/OT&E Timeline • MEM DTAP Equipment Site Survey and Connectivity Plan • On-going/Completed Trials Activities Status: - FAA/FDX MOU, Volpe/Boeing ARINC/SITA Trials Service Tasking - Trials SRMD - Test NCPs - Trials ISSM - Trials FTI Architecture/Provisioning - MEM Training and Procedures

  3. DTAP Development Status

  4. DTAP Milestone Deliveries and CHI Design Review Summary • SE2020 Contract Deliverables/DTAP Development On-going: • pDTAP installed in FAATC Data Comm lab • DTAP SSS Baseline Concept/Functional Requirements Mapping Complete • Initial PSAA, SSHA, SSPP delivered to FAA • Initial Operational DTAP delivery to FAATC 8/17 • Three DTAP CHI Design Reviews complete (May-June): - MEM, EWR, ATL facility and National Data Comm NATCA reps participation with Trials and Thales reps - Recommended CHI changes documented and incorporated into DTAP delivery schedules

  5. DTAP Test and OT&E Timeline

  6. DCL Trials Test Timeline (updated: 6/29/2012) Tech Center DTAP E-E Functional Testing (DTAP 1) SAT @ MEM DTAP 1&2 pDTAP DTAP 1&2 setup/prep Video crew @ Tech Center event (Sept. 13) AFN attempt with FedEx aircraft (to be arranged) event (July 17 & 18) DCL & AFN attempt with DCIT aircraft pre-arranged event (Aug 29 & 30) Conduct Thales install & checkout Controller OT&E (35) Dry & Prep Dry run & prep Conduct Training May 10 Aug 17 Aug 22 Sept 4 Sept 7 Sept 14 Sept 17 Oct 1 Nov 1 • Controller OT • Prep / Dry run & Conduct • System test case / bench avionics + TC aircraft • System test case / Boeing air lab • System test case / Airbus air lab • System test case / DCIT aircraft • Error conditions / failover • PTR fixes / regression • DTAP Test Report • Install & checkout • Training • SAT sub_test cases final • SAT sub_test cases functional testing/ FedEx aircraft • E-E Operational scenarios based on DCIT v1.0 doc / FedEx aircraft • Error conditions / failover in field env. • SAT Test Report • pDTAP / HADDS in box test • pDTAP / HADDS via FNTB Failover / Rev # test • pDTAP / HADDS / CSP Interface via FNTB + bench Avionics • pDTAP (applicable reqs/VRTM) testing with bench avionics • pDTAP testing via Boeing + Airbus air labs • PTR fixes / regression • Test Cases document final • pDTAP Quick Look Report

  7. MEM DTAP Equipment Site Survey Results

  8. MEM DTAP Equipment Site Survey Summary • System locations identified and space assigned by MEM SSC/Tech Ops-PASS - DTAP w/maintenance console: 12th floor, existing FAA rack (T1212) - DTAP operator monitor/keyboard/mouse: Tower Cab, C/D position • Connectivity plan complete • Trials equipment includes DTAP system, DTAP monitor/keyboard/ converters, CAT5 cable, fiber optic media converters, fiber patch cable • Trials utilizing existing spare fiber optic pairs (2) as assigned by Tech Ops • MEM Tech Ops will install two 115v/20A breakers with cabling from assigned DTAP rack space to Essential Power circuit breaker panel (T1212) - July completion - Data Comm PO funded via PA - ~$2,000 • FTI service order to include mini-demarc at the Basement Comm • Equipment Room Fiber Distribution Rack (B26-FOTS2).

  9. MEM Connectivity Plan • Consistent with existing, and approved by MEM SSC/Tech Ops-PASS • DTAP to Controller • C/D position keyboard/monitor connects to KVM-CAT5 converter • CAT5 from tower cab thru existing data conduit to 12th floor • CAT5 to KVM converter (within DTAP) • DTAP to FTI (for HADDS & CSP) • CAT5 from DTAP to fiber media converter • Fiber patch cable from media converter to existing fiber distribution panel (FOTS) • Existing fiber down to existing basement FOTS • Fiber patch from basement FOTS1 to media converter in FOTS2 rack • CAT5 from media converter to FTI punch block demarc in basement FOTS2 • FTI-installed CAT5 from demarc to FTI facility

  10. MEM DTAP Monitor Clearance Delivery Position • DTAP 15” display to reside beside TDLS 15” display (base mount) • Maintains clear visibility to airfield and gate areas from C/D and SUP positions • Desktop Keyboard/Mouse • KVM converter mounted in cabinet below Strip Printer DTAP TDLS

  11. 12th Floor Electronics Equipment Room (T1212) Cable Tray Power Conduit Assigned DTAP Rack Space Location 12th floor Fiber Distribution Panel (FOTS) Existing spare fiber between 12th floor and basement FOTS as assigned by MEM Tech Ops Fiber Media Converter

  12. 12th Floor Electronics Equipment Room (T1212) CAT5 data conduit access to Tower Cab MEM Tech Ops installed power cable run from DTAP rack to power panel in existing power conduit Existing fiber to basement B26 Assigned by MEM Tech Ops Fiber Media Converter ~52’ from Rack to Cab conduit Assigned DTAP Rack Space Location T1210 Non-FAA equipment room 115v / 20A DTAP Essential Power Panel / CBs

  13. Basement Comm Equipment Room (B26) • Contractors allowed 24 hour access with badge/proxy FOTS1/2 Fiber Distribution Racks FTI Owned Telco – Network Access Existing Fiber and Distro Panels to/from 12th floor (left) Assigned by MEM Tech Ops Fiber Media Converters (right) FTI to Cable CAT5/6 from FOTS1/2 Fiber Distribution Rack mini-demarc

  14. On-Going/Completed Trials Activities

  15. FAA/FDX MOU, Volpe/Boeing Trials Service Tasking • FAA/FDX MOU executed June, 2012: • Cooperation agreement between the parties • FDX starting systems work to accommodate DCL filing requirements (FRC DCL) and ARINC 620 DCL Copy messages and ACKS • Trials CSP Service Tasking via existing Volpe/Boeing contract vehicle: • POP from 5/1 – 12/1 • ARINC agreement complete (June) • SITA agreement pending completion (Boeing adding as Sub) • Both ARINC working now to get connectivity to the Tech Center Data Comm lab to allow initial pDTAP A/G testing (Proxy wavier granted by ISSM)

  16. Trials SRMD • Trials SRMD approved with all required signatures June 1, 2012 • Added to 2010 approved Data Comm PHA document covering Terminal and En Route

  17. Trials Activities – Trials Test NCPs • 2 Test NCPs have been approved via CCB: • HADDS configuration (IP and OARS) • Adding Rev # to HOST HNL HADDS CMS data • HADDS, HOST ZME patch deployments in late July • MEM Space and Power Test NCPs (2) submitted for SME review and CCB assignment • Additional Test NCP submittal pending: • Create a MEM FDIO/PCRCU Echo Port for DTAP to filter out Rev # data

  18. Trials ISSM • Initial ISSM compliant Trials documentation review complete by ISSM (June) • Updated ISSM requested documentation complete and resubmitted to ISSM (7/09) • ISSM ruling on ATL NESG proxy requirement pending: • Trials team and support (Guy C and Tony S) promoting IP/NAT Level 3 proxy requirement • Due to DTAP internal security controls – no further FEP/BEP security required for Trials • FTI 128k provisioning on hold until ISSM approves of Trials connectivity plan (Sandy to facilitate with FAA FTI Mgt)

  19. FTI Architecture/Provisioning • pDTAP installed in FAATC Data Comm Lab • Initial HADDS, Avionics Testing Pending (DM25, UM73) • ARINC/SITA Connections Pending • No initial Proxy required • N39 primary FAA A/G Test AC • Industry AC (+Boeing/Airbus) testing planned • Initial DTAP functional testing starts 8/17 • ARINC/SITA Connections via ATL NESG • ISSM decision pending on Proxy Requirement • ZME HADDS remote patch scheduled for deployment in late July (DTAP Ips and OARS table) • NAIMES assigned DTAP Ips (2) • FTI provisioning for two DTAP 128k FTI connections at MEM ATCT FAATC FNTB MEM OPSIP

  20. MEM Training and Procedures • Draft MEM Training and Procedures compete: • Reviewed with MEM ATC representatives (6/28) • Local MEM procedures incorporated • MEM DTAP Training starts Oct-Nov, 2012 • July/Aug meeting planned (via GoTo) with MEM, EWR, ATL facility reps to review local procedure inputs to the umbrella Training and Procedures documents

  21. Questions ? KMEM