C6 Science Test Plan

C6 Science Test Plan. Draft Version 1 07/22/2009 Email your feedbacks to Sadashiva.Devadiga-1@nasa.gov. Assumptions. C6 L1B delivery expected by July 31, 2009 Following C6 Atmospheric products should be available by Sept 30 2009

arien
Download Presentation

C6 Science Test Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. C6 Science Test Plan Draft Version 1 07/22/2009 Email your feedbacks to Sadashiva.Devadiga-1@nasa.gov

  2. Assumptions • C6 L1B delivery expected by July 31, 2009 • Following C6 Atmospheric products should be available by Sept 30 2009 • MOD35 (for LST, Snow and Sea_Ice, All land PGEs except LSR and Fire) • MOD07 (for LST) • Deep Blue Aerosol for Terra and Aqua for years 2007and 2008 (for LST) • Final Land Cover product (MOD12Q1) and land water mask for use in C6 reprocessing by August 31, 2009 • C6 MOD09 (PGE11) first version available by early October 2009

  3. Major C6 Science Tests • C6 L1B Test (Aqua + Terra) in Aug 2009 • 2 16-day Global Test (2003001 and 2003193) • Compare C5 L1B vs C6 L1B • C6 Land Baseline Test (Aqua + Terra) in Aug/Sept 2009 • 2 16-day Global Test (2003001 and 2003193) • Compare C5 Land with C5 L1B vs C5 Land with C6 L1B • C5 Land products with C6 L1B will be used as baseline for evaluation of C6 changes. • 1st 16-day Global Test in October 2009 • C6 L1B, Cloud Mask and Atmospheric Profile • First C6 updates to land PGEs • All available land PGEs will be run with the first C6 version of PGE11 • For LST this will be the C6 baseline Test with the C6 Cloud Mask and Atmospheric Profile • 2nd 16-day Global Test in Nov/Dec 2009 • Second C6 updates to Land PGEs • 1st and/or 2nd revisions to LST C6 algorithm • N-tiles 3-month time series Test in Dec 09/Jan 2010 • All land PGEs • Test and evaluation to conclude by end of Feb 2010 • Final Global Test/Time series Test in Feb/March 2010 • For all/selected PGEs as required

  4. Time Line of Testing and PGE Deliveries (1/3) 08/01/09 09/01/09 10/01/09 10/30/09 Land-Cover, Land-water mask PGE11 C6.2 Daily LSR PGE16 C6.1 LST PGE11 C6.1 Daily LSR C6 MOD35, MOD07, Land PGEs 1st drop C6 L1B PGE21 8DAY-LSR gapfilled Daily LSR Test evaluation and C6 development Daily LSR Test evaluation and C6 development Complete PGE11 C6 baseline test – 1 year Repeat PGE11 C6 1-year global test 1st 16-day Global Test C6 LST Baseline Test C6 L1B Test C6 Land Baseline Test – 16-day Global

  5. Time Line of Testing and PGE Deliveries (2/3) 11/01/09 12/01/09 01/01/10 PGE16 C6.2 LST PGE16 C6.3 LST Land PGEs 2nd Drop Land PGEs 3rd Drop Repeat 16-day Global Test N-tile 3-month time series

  6. Time Line of Testing and PGE Deliveries (3/3) 02/01/10 03/01/10 04/01/10 Integration of C6 PGEs to MODAPS Land PGEs Last drop Complete Time series test and evaluation Final Science Test Start of C6 Processing