Texas-New Mexico Power & CenterPoint Energy Alvin 345/138 kV Tie Project TAC – 01/04/2007

Loading in 2 Seconds...

play fullscreen
1 / 7

Texas-New Mexico Power & CenterPoint Energy Alvin 345/138 kV Tie Project TAC – 01/04/2007 - PowerPoint PPT Presentation


  • 91 Views
  • Uploaded on

Texas-New Mexico Power & CenterPoint Energy Alvin 345/138 kV Tie Project TAC – 01/04/2007. Description of Project - 2007. Build 345/138 kV station and loop PH Robinson to Oasis 345 kV line into this station Loop existing Hastings to Alvin 138 kV line into new station

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Texas-New Mexico Power & CenterPoint Energy Alvin 345/138 kV Tie Project TAC – 01/04/2007' - arawn


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
description of project 2007
Description of Project - 2007
  • Build 345/138 kV station and loop PH Robinson to Oasis 345 kV line into this station
  • Loop existing Hastings to Alvin 138 kV line into new station
    • Rebuild this line from new station to Hastings
  • Rebuild Hastings to Friendswood 138 kV line
  • Cost $19.4 M (2006 dollars)
associated long term projects 2010
Associated Long Term Projects – 2010+
  • Rebuild South Shore to P.H. Robinson 138 kV line
  • Rebuild Friendswood to Seminole 138 kV line
  • Cost $5.1 M (2006 dollars)
slide4

Projects Needed for Reliability

  • Generation re-dispatch will not be able to relieve post-contingency loading during peak load by 2007
  • Occurs with single and multiple line outages
options considered
Options Considered
  • TNMP considered eight options
  • ERCOT studied the two least expensive of TNMP’s eight options in depth
  • Recommended Project is the least expensive option considering the long term (2015) needs of the area
slide6

Stakeholder Review

  • The Stakeholder review period for this project was held in August 2006
  • There were no dissenting comments on this package of projects and TNMP resolved all questions
slide7

ERCOT Support for the Project

ERCOT supports the need for this project, as described, and will be requesting that it be endorsed by the Board