PIP Update. Sept 26 2012. Agenda. Summary Update Current Activities Updates/Talks: Ken Domann - Schedule Update and Statusing Ryan Crawford - Linac MCC/Transformer, Hatch, Booster Transformers, Anode Supply Dave Hixson - Booster LCW. Update. General Info Current Work

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' PIP Update' - aoife


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Pip update

PIP Update

Sept 26 2012


Agenda
Agenda

  • Summary Update

    • Current Activities

      Updates/Talks:

  • Ken Domann - Schedule Update and Statusing

  • Ryan Crawford - Linac MCC/Transformer, Hatch, Booster Transformers, Anode Supply

  • Dave Hixson - Booster LCW


Update
Update

General Info

  • Current Work

    • Booster RF cavity – RF5 is back (~11 weeks) RF 6 work has begun

    • Transformers (Linac and Booster) Update talk today

    • LCW – Started Refilling yesterday – Update talk today

    • RFQ – Electrical work underway, Install will start next week

    • HPower RF – A 1.4M is waiting for 2nd floor signature

    • High Power Ferrite Testing – No news

    • Booster Absorber – Shelving installed – Install Procedure Written

    • Linac Modulator – Need to firm up FY13 plan – Planning meeting?

    • Booster Solid State – 82 amplifiers checked, LLRF chassis' are completed

    • Booster Modulator work – 10 done yet?

    • Tuner with new ferrite – Any tests yet?

      Shutdown - comments (Fernanda, Todd, Mary – updated the schedule yesterday and will meet tomorrow at 10 in the Huddle )

      END OF Fiscal Year No guarantee that reqs in process will be approved! Working to finish rest of requisitions for FY12. Last day today – may actually be closed. I have no more reqs to sign.


Upcoming
Upcoming

  • Finish up RLS – Update Request went out this morning

    • Lots of progress

    • Need to work through the FY13 budget( labor/M&S) into RLS

  • End of Fiscal year

    • Today – No more requisitions (final numbers – next week)

    • Reports (October)

      • PMG

      • Quarterly Report

    • Will have special Wednesday meeting with Ann to discuss FY13

  • PIP talk at PAC (Oct)

  • SAD meeting last week – information exchanged between PIP and safety with some items identified to be worked on.

  • No news on lab budget meetings last week – lots of issues!

  • Stuart asked us to think about University help for PIP – Items?


Talks
Talks

  • Ken Domann - Schedule Update and Status

  • Ryan Crawford - Linac MCC/Transformer, Hatch, Booster Transformers, Anode Supply

  • Dave Hixson - Booster LCW