BLACK START PROCEDURES:REVIEW OF STARTUP POWER TO NTPC,RGM. WHY ISLANDING OF NTPC UNITS WITH A RADIAL LOAD IS NOT PREFERABLE. NTPC UNITS ARE NOT ON FREE GOVERNOR MODE. AS FAULT LEVEL OF THE BUS IS VERY LOW LARGE VOLTAGE FLUCTUATIONS ARE LIKELY.

Download Presentation

BLACK START PROCEDURES:REVIEW OF STARTUP POWER TO NTPC,RGM.

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Black start procedures review of startup power to ntpc rgm

BLACK START PROCEDURES:REVIEW OF STARTUP POWER TO NTPC,RGM.

WHY ISLANDING OF NTPC UNITS WITH A RADIAL LOAD IS NOT PREFERABLE

  • NTPC UNITS ARE NOT ON FREE GOVERNOR MODE.

  • AS FAULT LEVEL OF THE BUS IS VERY LOW LARGE VOLTAGE FLUCTUATIONS ARE LIKELY.

  • FREQUENCY CANNOT BE CONTROLLED IN AN ACCEPTABLE BANDWIDTH DUE TO LOW POWER NUMBER IN THE SYSTEM.

  • PHASE IMBALANCES,ESP.DUE TO TRACTION LOADS MAY CAUSE SECONDARY COLLAPSE IN THE ISLAND.