BLACK START PROCEDURES:REVIEW OF STARTUP POWER TO NTPC,RGM. WHY ISLANDING OF NTPC UNITS WITH A RADIAL LOAD IS NOT PREFERABLE. NTPC UNITS ARE NOT ON FREE GOVERNOR MODE. AS FAULT LEVEL OF THE BUS IS VERY LOW LARGE VOLTAGE FLUCTUATIONS ARE LIKELY.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha

Download Presentation

BLACK START PROCEDURES:REVIEW OF STARTUP POWER TO NTPC,RGM.

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


BLACK START PROCEDURES:REVIEW OF STARTUP POWER TO NTPC,RGM.

WHY ISLANDING OF NTPC UNITS WITH A RADIAL LOAD IS NOT PREFERABLE

  • NTPC UNITS ARE NOT ON FREE GOVERNOR MODE.

  • AS FAULT LEVEL OF THE BUS IS VERY LOW LARGE VOLTAGE FLUCTUATIONS ARE LIKELY.

  • FREQUENCY CANNOT BE CONTROLLED IN AN ACCEPTABLE BANDWIDTH DUE TO LOW POWER NUMBER IN THE SYSTEM.

  • PHASE IMBALANCES,ESP.DUE TO TRACTION LOADS MAY CAUSE SECONDARY COLLAPSE IN THE ISLAND.