[email protected] COMPREHENSIVE WATER MANAGEMENT SOLUTIONS PVT. LTD. www.cwms.co.in. INTEGRATED WATER MANAGEMENT FOR AUTO INDUSTRY, AT MOSHI, PUNE - INDIA. Comprehensive Water Management Solutions Pvt. Ltd. NO TAP WATER SOURCE THE ONLY SOURCE WAS ‘RAIN’ WATER DEMAND WAS 33,500 LITS/DAY.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' cwms.co' - anise


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

[email protected]

COMPREHENSIVE WATER MANAGEMENT SOLUTIONS PVT. LTD.

www.cwms.co.in


INTEGRATED WATER MANAGEMENT

FOR AUTO INDUSTRY,

AT MOSHI, PUNE - INDIA

Comprehensive Water Management Solutions Pvt. Ltd.


Comprehensive Water Management Solutions Pvt. Ltd.


AIM WAS TO ACHIEVE

‘SELF SUFFICIENCY’

IN WATER

Comprehensive Water Management Solutions Pvt. Ltd.


The solution was rain water harvesting and ground water recharge
THE SOLUTION WAS‘RAIN WATER HARVESTING’AND ‘GROUND WATER RECHARGE’

Comprehensive Water Management Solutions Pvt. Ltd.


Entient rain water harvesting in rajasthan
ENTIENT RAIN WATER HARVESTING IN RAJASTHAN

Comprehensive Water Management Solutions Pvt. Ltd.


ENTIENT

RAIN WATER HARVESTING IN SOUTH INDIAN TEMPLES

Comprehensive Water Management Solutions Pvt. Ltd.


IN INDIA, AVERAGE RAINFALL

IS 117 CM.

Comprehensive Water Management Solutions Pvt. Ltd.


However

In Rajasthan 20 cm.

and in Cherrapunji 1168 cm.

Comprehensive Water Management Solutions Pvt. Ltd.


But it rains in short spell that is just 90 days how to use this
BUT IT RAINS IN SHORT SPELL, THAT IS JUST 90 DAYS.HOW TO USE THIS?

Comprehensive Water Management Solutions Pvt. Ltd.


WATER DEMAND

TOTAL MANPOWER OF FACTORY : 500 NOS.

REQUIREMENT AS PER NORMS:

  • Drinking 500 x 3 lits = 1,500 lits/day (1.5 cu.m/day)

  • Hand wash 500 x 10 lits = 5,000 lits/day (5.0 cu.m/day)

  • Sanitation 500 x 30 lits. = 15,000lits/day (15.0 cu.m/day

  • Water for Processing = 2,000 lits/day (2.0 cu.m/day)

  • Water for Landscaping = 10,000 lits/day (10.0 cu.m/day)

  • HENCE THE TOTAL WATER NEED WAS 33,500 LITS. /DAY (33.5 cu.m/day)

    NOTE: 1 cu.m = 1,000 lts

Comprehensive Water Management Solutions Pvt. Ltd.


LOCATION : DEHU ALANDI ROAD.

PLOT AREA : 12,000.00 SQ.M.

SLOPE FROM : SOUTH TO NORTH WITH A DIFF. OF 3.0 M

NO TAP WATER SOURCE.BOREWELL 15 CU.M YIELD

Comprehensive Water Management Solutions Pvt. Ltd.


BUILT UP AREA DETAILSBUILT UP AREA OF MAIN FACTORY : 4,800.00 SQ.MUTILITY BUILDING : 200.00 SQ.M TOTAL BUILT UP AREA : 5,000.00 SQ.M

Comprehensive Water Management Solutions Pvt. Ltd.


Water potential of site
WATER POTENTIAL OF SITE

  • ROOF WATER 2,448.0 cu.m

    (4,800 X 0.6 X 0.85 = 2,448 cu.m)

  • STORM WATER 2,160.0 cu.m

    (7,200 X 0.60 X 0.50 = 2,160 cu.m)

  • GROUND WATER 15 .0 cu.m/day

  • WASTE WATER 16.0 cu.m/day

    ( 500 X 40 X 0.80 = 16.0 cu.m)

    AGAINST THE DEMAND OF 33,000 lits/day

    33 cu.m/day

NOTE: 1 cu.m = 1,000 lts.

Comprehensive Water Management Solutions Pvt. Ltd.



ROOF WATER FOR DRINKING – 2,448 cu.m 4,800 x 0.6 x 0.85 = 2,448 cu.m ROOF WATER - DOWN TAKE PIPE - SAND FILTER - RO FILTER,UG TANK 16X10X2M - DRINKING WATER POINTS&OVERFLOW TO DRY BORE WELL While drinking water requirement is 3,00,000 lts.

Comprehensive Water Management Solutions Pvt. Ltd.


Pipe for collection of roof water
PIPE FOR COLLECTION OF ROOF WATER

DOWN TAKE FILTER

Comprehensive Water Management Solutions Pvt. Ltd.


Rain water testing report
RAIN WATER TESTING REPORT

Comprehensive Water Management Solutions Pvt. Ltd.


STORM WATER FOR GROUND WATER RECHARGE – 2,100 CU.M7,200 x 0.6 x 0.5 = 2,160 cu.mSURFACE WATER – CHANNEL - GUTTERS - RAW WATER FROM BORE WELL - U.G.TANK - SOFTENING PLANT - TOILETS & PROCESSINGBecause of recharging treatment the borewells started giving more yield every year

Comprehensive Water Management Solutions Pvt. Ltd.


STORM WATER CHANNELS AND RECHARGE BORE WELL

Comprehensive Water Management Solutions Pvt. Ltd.


Section of recharge borewell
SECTION OF RECHARGE BOREWELL

IT WAS FOUND THAT DUE TO CONTINUOUS RECHARGING THE GROUND WATER YEILD HAS INCREASED SUBSTANTIALLY

Comprehensive Water Management Solutions Pvt. Ltd.


Ground water testing report
GROUND WATER TESTING REPORT

Comprehensive Water Management Solutions Pvt. Ltd.


Waste water recycling waste water stp plant collection tank water for landscaping
WASTE WATER RECYCLINGWASTE WATER - STP PLANT - COLLECTION TANK - WATER FOR LANDSCAPING

Comprehensive Water Management Solutions Pvt. Ltd.


Distribution network
DISTRIBUTION NETWORK

Comprehensive Water Management Solutions Pvt. Ltd.


Water usuage table
WATER USUAGE TABLE

NOTE: 1 cu.m = 1000 lts

Comprehensive Water Management Solutions Pvt. Ltd.


Architectural details for maximum collection of water
ARCHITECTURAL DETAILS FOR MAXIMUM COLLECTION OF WATER

  • NORTH LIGHT ROOF TRUSS WITH GUTTER SLOPE ON BOTH SIDES .

  • ROADS SLOPED ON ONE SIDE WITH CAMBER.

  • PUSH COCKS IN TOILET.

  • ALLOCATION OF SERVICES AS PER NATURAL GROUND SLOPE.

  • EMPHASIS ON METICULOUS EXECUTION.

Comprehensive Water Management Solutions Pvt. Ltd.


WATER COST WITHOUT ANY WATER MANAGEMENT PLANWOULD HAVE BEENRs. 330,000/yr.330 x 1,000 = Rs. 3,30,000(330 = actual working days)( App. 35 days public holidays)Rs. 500/tanker and 2 tankers/day

Comprehensive Water Management Solutions Pvt. Ltd.


As against actual project cost was rs 6 75 000 so the payback time just two years
AS AGAINSTActual project cost was Rs. 6,75,000/-So the payback timejust two years

Comprehensive Water Management Solutions Pvt. Ltd.


Results
RESULTS

  • The entire plan of ‘Integrated Water Management’ was achieved by – detail augmentation plan, collection, purification and plumbing net-working plan.

  • Every year the water yield is increasing as ground water table is also improved substantially because of the treatments.

Comprehensive Water Management Solutions Pvt. Ltd.


FACTORY AT MOSHI, PUNE (INDIA)

Comprehensive Water Management Solutions Pvt. Ltd.


Our mission is to promote sustainable WATER MANAGEMENT as per the supply and demand without disturbing the natural balance and make it available for everyone.

Comprehensive Water Management Solutions Pvt. Ltd.


THANK YOU.