Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 Sept 27 Monthly Review Gunther Haller haller@slac.stanford.edu (650) 926-4257. TEM/TPS Status. Status Qual unit review still to occur

anisa
Download Presentation

GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 Sept 27 Monthly Review Gunther Haller haller@slac.stanford.edu (650) 926-4257

  2. TEM/TPS Status • Status • Qual unit review still to occur • 19 flight units delivered to I&T • 2 TPS units removed from Twr A and Twr B were partially modified • To do (low priority) • Complete modification • Vibration • End data package review

  3. PDU Status and Schedule • 1st unit (flight) • In hands of I&T • 2nd unit (spare) • Progress since last month • Boards conformal coated • Includes • Coating • AF QC, touchup, QC • SLAC (customer) source-inspection, touch-up, CSI • Integration into enclosure • Started wiring • Lower priority compared to assembly of SIU modules, but progressing, estimated delivery to I&T end of December

  4. GASU Status and Schedule • First Unit • Progress since last month • Received final box • Passed Safe-to-mate (without power) • Passed Stray-voltage tests (with power) • Passed Comprehensive Performance Tests • Thermal-cycled • Passed post TC tests • Vibrated to proto-flight levels • Passed post-vib tests • Started thermal-vacuum test, expected completion Nov 7 • EMI left, if proto-flight EMI: 2 weeks, if flight acceptance: 1 day • GASU available Nov 9 or Nov 23, depending on EMI decision • Schedule for 2nd unit • Progress since last month • QC&CSI, rework and again QC&CSI of DAQ and power-supply boards (pre-coat) • Boards are being installed in enclosure with harness • In about 3 weeks the box will be sent to SLAC for pre-coat testing, followed by conformal coat and environmental testing • Lower priority compared to SIU/HCB but still progressing • (Mid January estimated delivery to I&T)

  5. SIU Protoflight • Protoflight SIU crate • Progress since last month • Received backplane assembly (backplane 2412) • Integrated in enclosure • Passed short/open test • Integrated SIB2205, LCB2225 CPS2233, RAD750-CPU • All from flight assembly line, SIB has chlorine-contaminated EEPROM • Passed environmental testing • Passed Comprehensive Performance testing • Thermal-cycled • Passed testing • Vibrated to proto-flight levels • Passed testing • Thermal-Vacuum tested (proto-flight limits) • Full EMI tested (passed qualification tests, conductive/radiative) • Mass and CG measured

  6. First Flight Crate • Progress since last month • Modules • Backplane 2414/2428 • integrated in crate 2513 • SIB 2207 • shipped to SLAC and module tested • LCB 2227 • shipped to SLAC and module tested • CPS 2235 • shipped to SLAC and module tested • RAD750 14/2516 • Crate integrated, tested • Thermal-cycle, tested • Vibrated, tested • Thermal vacuum tested • EMI, tested • Mass measured • No failure • Working on web-site to list test results, closing of NCR’s

  7. Second Flight Crate • Progress since last month • Modules • Backplane 2415/2429 • harness assembly completed, coated/QC/CSI/touch-up/delivered to SLAC, open/short tested • Integrated in crate 2527 • SIB 2208 • shipped to SLAC and module tested • LCB 2226 • coated, shipped to SLAC, tested • CPS 2238 • shipped to SLAC and module tested • RAD750 15/2517 • Crate tested • Thermal-cycle, tested • Vibrated, tested • Thermal vacuum tested • EMI, tested • Mass measured • No failure • Working on web-site to list test results, closing of NCR’s Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch-up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

  8. Third Flight Crate • Progress since last month • Modules • Backplane 2420/2433 • harness assembled, coated, shipped to SLAC, open/short tested • Integrated in crate 2522 • SIB 2206 • xrayed, shipped to Silver, tested, shipped to SLAC, tested, shipped to AF, coated, shipped to SLAC, tested • LCB 2228 • coated, shipped to SLAC, tested • CPS 2239 • coated, shipped to SLAC, tested • RAD750 17/2518 • Crate integrated, tested • Thermal-cycle, tested • Vibrated, tested • Waiting for thermal vacuum testing (GASU is in TV chamber) • EMI, will be tested this week before TV • Mass measured • No failure up to now • Estimated completion of testing: Nov 15 • Working on web-site to list test results, closing of NCR’s Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch-up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

  9. Fourth Flight Crate • Progress since last month • Modules • Backplane 2419/2434 • harness assembled, coated, shipped to SLAC, open/short tested • Integrated in crate 2523 • SIB 2209 • flying probe tested, assembled, shipped to SLAC, xrayed, shipped to Silver, tested, shipped to SLAC, tested, shipped to AF, coated, shipped to SLAC, tested • LCB 2229 • flying probe tested, assembled, shipped to SLAC, xrayed,, tested, shipped to AF, coated, shipped to SLAC, tested • CPS 2240 • assembled, shipped to SLAC, tested, shipped to AF, coasted, shipped to SLAC, tested • RAD750 18/2519 • Crate integrated, tested • In Thermal-cycle • To be done • Vibration • Thermal vacuum • EMI • Mass • Estimated completion: Nov 22 Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch-up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

  10. Fifth Flight Crate • Progress since last month • Modules • Backplane 2418/2431 • harness assembled, coated, shipped to SLAC, QA issues, shipped back to AF, in rework, will be shipped to SLAC early next week • Will be in crate 2523 • SIB 2210 • assembled new EEPROM, flying probe tested, assembled, shipped to SLAC, xrayed, shipped to Silver, tested, shipped to SLAC, tested, shipped to AF, in coating • LCB 2230 • flying probe tested, assembled, shipped to SLAC, xrayed,, tested, shipped to AF, coated, in QA/CSI, will be shipped to SLAC tomorrow • CPS 2234 • Assembled, shipped to SLAC, tested. Shipped to AF, in coating • RAD750 13/2528 • Crate to be integrated • To be done • TC • Vibration • Thermal vacuum • EMI • Mass • Estimated completion: Dec 6 Coated really stands for: take hardware off (rails, etc), coat, QC, touch-up, CSI, touch-up, QC/CSI, add hardware, bond, QC/CSI, stake, QC/CSI

  11. Spare crates • Modules • 2 Backplanes • Ready for integration Nov 30, Dec 7 • 2 SIB’s • Ready for integration Nov 19, Nov 28 • 2 LCB’s • Ready for integration Nov 19, Nov 28 • 2 LCB’s • Ready for integration Nov 23, Nov 23 • Estimates for Spare Crate availability • Dec 16 & Dec 23

  12. Harness Interconnect Box (HIB) • Task: Integrate, stake, pre-tested harness into (SIU) enclosure • Progress since last month • Assembled 5 HIB’s at SLAC • Two vibrated • 3 more about to be vibrated • Ready for hand-off to I&T early next week

  13. Heater Control Box (HCB) • 6 Boards for 3 boxes assembled (2 flight + 1 spare) • 4 Boards for 2 boxes conformal coated • 2 boards integrated into one box with harness • In QA at AF • 2nd box will be in QA early next week • Then TC/TV/vib/EMI at SLAC • Estimated delivery of 2 HCB’s to I&T: Nov 24

  14. cCPI Connector Solder Joint Slide • SLAC Qual testing of sample boards assembled at Aeroflex • Non-flight, only connectors were assembled on cCPI board for short/open testing of solder joints • Testing was all completed without failures • Presentation at • http://www-glast.slac.stanford.edu/Elec_DAQ/DAQ-Hardware/SIU-EPU/xray/xray-qual.htm • Overall cCPI solder joint results on flight boards • 5 flight backplanes accepted to use-as-is, see following 5 slides for detailed results • Process is • SLAC looked at xrays, had touched up candidates • Then GSFC supplied a list fo pins to be touched up • SLAC went thru and identified pins which are used • Those were discussed and some were touched up • Plug-in cards • Same process as with backplanes • Maybe 1 or 2 pins on some boards which GSFC likes to have touched-up • Discussed and agreed on boards already integrated • SLAC is touching up all boards not integrated yet and supply new xrays (in progress)

  15. First Flight Backplane 2414 • 22 pins identified on GSFC list out of 2,000 pins • Not used (16 pins) • Already identified on SLAC list • X1: P5-D11; P5-C12; P5-D12; • X2: P1-B17 • X3: P1-B17 • Not used from remaining identified (X1-P5, X2-P1 not used as stated) • X1: P5-E11 • X2: P1-A19 • X2: P2-C10, B11, C11, D11; P4-C6 • X3: P1-B2 ; P1-B6 (red+5); P5-B2 (ch-gnd); P5-C14 (red+5), P4-B21 (redGND); • X4: P5-B5 (red+3.3) • Used • Already identified on SLAC list • X1: P1-B15 (Frame#); • X3: P1-A7 (AD30); • Not on SLAC list • X1: P1-C23 (AD3) ; • X3: P1-D16 (stop_n) • Conclusion • GSFC accepted X1-P1.C23 and X3-P1.D16 as is but wanted to improve X1-P1.B15 and X3-P1.A7 • Those 2 pins were already touched-up since they were on SLAC’s original “nice-to-improve” list but no xrays were taken after touch-up since pins were already acceptable in SLAC’s view before touch-up • Final decision: use-as-is

  16. Second Flight Backplane 2415 • 18 pins identified on GSFC list out of 2,000 pins • Not used • Already identified on SLAC list (7 pins) • X2: P1-B3; P4-A15; P4-B23; • X3: P1-B8; P2-C12; J4-C1, J4-C16 • Not used from remaining identified • X1: P1-A19 (3.3V, one of 7 pins, not needed) • X3: P2-B12; P3-C1 (red+5), C3 (red+5), E4 • X4: P1-B1 • Used • Already identified on SLAC list • X4: P1-C23(AD3); P4-C11(EI_PRIM_5_N); P4-C21(EI_PRIM_2_P) • Not on SLAC list • X1: P1-B19 (AD15), P1-A20 (AD12) ; • Conclusion • GSFC accepts all except X4-P1.C23 • That one pins was already touched-up since it was on SLAC’s original “nice-to-improve” list but no xrays were taken after touch-up since pins were already acceptable in SLAC’s view before touch-up • Final decision: use-as-is

  17. Third Flight Backplane 2420 • 5 pins identified on GSFC list out of 2,000 pins • Not used • Already identified on SLAC list • None • Not used from remaining identified • X1: P2-C21 • X2: P1-D25 • X3: P2-E8, B13 • X4: P5-C22 • Used • None • Conclusion • Final decision: use-as-is

  18. Fourth Flight Backplane 2418 • 17 pins identified on GSFC list out of 2,000 pins • Not used • Already identified on SLAC list • None • Not used from remaining identified • X1: P2-B5, P4-E7, D8, E8, D9 (P4 not used) • X2: P1-D11, B23, B24, C24; P2-B1, C1; (P1, P2 not used) • X2: P4-C9 (red+5); P5-A5 (red-28) • X4: P5-D21 • Used • Already identified on SLAC list • None • Not on SLAC list • X1: P2-B6 (GBM RDNT) • X3: P1-E7 (AD27) • Result • SLAC agreed to touch-up those 2 pins and also rexrayed the board • Conclusion • GSFC agrees that pins were improved • Final decision: use-as-is

  19. Fifth Flight Backplane 2419 • 6 pins identified on GSFC list out of 2,000 pins • Not used • Already identified on SLAC list • X1: J5-C13, B15 • Not used from remaining identified • X1: P5-C15, A18 (X1-P5 not used) • X3: P2-D10 • X4: P2-A10 • Used • None • Conclusion • Final decision: use-as-is

  20. Level 3 Milestone Count

  21. Level 3 Milestone List

  22. Level 3 Milestone List

  23. Level 3 Milestone List

  24. Cost Report

  25. FTE Report (DOE/NASA-funded only)