OOMC and Local RPRS Settlement Alignment. January 2007 WMS Meeting Ino Gonzalez ERCOT Settlements. Objectives. Align Settlement of Local RPRS Deployments with that of OOMC. Reasons for Proposal. Potomac Economics Recommendation Both Services Utilized to Solve Local Constraints

Download Presentation

OOMC and Local RPRS Settlement Alignment

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Oomc and local rprs settlement alignment

OOMC and Local RPRSSettlement Alignment

January 2007

WMS Meeting

Ino Gonzalez

ERCOT Settlements


Objectives

Objectives

  • Align Settlement of Local RPRS Deployments with that of OOMC


Reasons for proposal

Reasons for Proposal

  • Potomac Economics Recommendation

    • Both Services Utilized to Solve Local Constraints

    • Consistent Settlement Methodology

    • Include Start-Up Claw-Back

    • Include Claw-Back Three Hours After End of Deployment

  • WMS Request for PRR proposal


Reasons for oomc deployments

Reasons for OOMCDeployments

6.5.10 Out of Merit Capacity and Out of Merit Energy Services

ERCOT will use OOMC and OOME Services to procure additional capacity and energy required to provide reliable ERCOT System operation, or to effectively manage Local Congestion as determined

by ERCOT.


Reasons for local rprs deployments

Reasons for Local RPRS Deployments

6.8.1.11Local Congestion Replacement Reserve Payment to QSE

The QSE for a Resource selected to provide RPRS to resolve Local Congestion that actually reconnects to the ERCOT Transmission Grid and starts the unit in order to provide RPRS will be paid both the Resource Category Generic Startup Cost for starting the unit and the Resource Category Generic Minimum Energy Cost less the MCPE for operating at the Low Sustainable Limit (LSL) as set forth in the Resource Plan for that unit during the instructed interval (s). If the MCPE during the intervals of an hour in which ERCOT deploys a Resource for RPRS provides revenue in excess of the hourly cost to start and operates the unit at LSL, the QSE representing the Resource may retain any such excess revenue.


Settlement of oomc deployments

Settlement of OOMC Deployments

If RPRS Bid Price exists,

Then:

PCOOM = (-1)*Min [(BPRP * COOMRP), (PS + PO)]

Else:

PCOOM= -1 * (PS + PO)

Where:

PCOOM = OOMC Payments ($)

BPRP = Bid Price for Replacement Reserve ($/MW)

COOMRP = OOMC Awarded Capacity (MW)

PS = Start Up Price

PO = Operating Price


Settlement of oomc deployments1

Settlement of OOMC Deployments

If the unit is deemed to be on-line,

Then:

PS = 0

PO = ∑ [(RCGMEC – MCPE) * MIN(LSL/4, MR) ]

Else:

PS = Max [ 0, ( RCGSC – { ∑ (MCPE * MR) }) ] / # of instructed hours

PO = ∑ [(RCGMEC – MCPE) * MIN(LSL/4, MR) ]

Where:

RCGMEC = Resource Category Generic Minimum Energy Cost

RCGSC = Resource Category Generic Startup Cost

LSL = Resource Low Sustainable Limit

MCPE = Balancing Energy Market Clearing

MR = Actual Metered Output of the Resource

Clawback


Settlement of oomc deployments2

Settlement of OOMC Deployments

If resource continues to remain online after the instructed intervals

Then:

CRCGSC = ∑ (MCPE – RCGFC) * MR

If CRCGSC > 0 & Total PS>0

PS = Max(0,[ RCGSC – ∑ (MCPE * MR) - CRCGSC ]) / # hours

Else

PS = Max(0,[ RCGSC – ∑ (MCPE * MR) ]) / # hours

Where:

CRCGSC = Charge Against the Resource Category Generic Startup Cost

Clawback

Clawback

Clawback


Settlement of local rprs deployments

Settlement of Local RPRS Deployments

Current Methodology

LPC= -1 * Max(0, LPS + LPO)

If unit is deemed to be Off-line,

Then:

LPS = RCGSC / N

LPO = ∑ [(RCGMEC – MCPE) * MIN(LSL/4, MR) ]

Proposed Methodology

PS (LPS)= [ RCGSC – ∑ (MCPE * MR) - CRCGSC ] / # hours

PO (LPO) = ∑ [(RCGMEC – MCPE) * MIN(LSL/4, MR) ]

Where:

LPC = PCOOM = Local RPRS Payments ($)

LPS = PS = Price for starting the resource

LPO = PO = Price for operating the resource

N = Number of hours of procurement

Clawback


Conclusion and recommendation

Conclusion and Recommendation

  • No significant difference between OOMC and Local RPRS Settlements

  • Elimination of significant manual process to identify multiple startup payments for same resource.

  • Align Settlements of OOMC and Local RPRS