html5-img
1 / 14

SmartMeter TM Steering Committee Update – August 2012

SmartMeter TM Steering Committee Update – August 2012. Agenda. Monthly Updates Release Status Update Deployment Status Update Schedule Update Deployment Update Budget Status – Expenditures by Workstream Budget Status – Benefits Issues / Risks Summary Program Metrics Appendix

Download Presentation

SmartMeter TM Steering Committee Update – August 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SmartMeterTMSteering Committee Update – August 2012

  2. Agenda • Monthly Updates • Release Status Update • Deployment Status Update • Schedule Update • Deployment Update • Budget Status – Expenditures by Workstream • Budget Status – Benefits • Issues / Risks Summary • Program Metrics • Appendix • Project Deployment Plan Progress • Contingency Reconciliation • SmartMeterTM Acronyms

  3. Release Status Update Actions/Status Challenges

  4. Deployment Status Update Challenges Actions/Status

  5. Schedule Update 2013 2012 Jan Mar Aug Sep Dec Feb Oct Nov Jun Jul Feb Apr Jan Mar May IT Release Deployment All in-scope functionality completed SM Operations Center Field Delivery 9.0M Meters/Modules in service Begin SmartMeter Opt-Out Program Begin NEMS pilot Begin NEMS deployment Begin Transformer Rated Pilot Release additional work per 2012 – 2013 Deployment Plan Benefits Meter Reading Reductions (ITD) 621 Positions Captured Legend Forecasted Milestone (delay) Baseline Milestone Milestone Met Milestone TBD Approved Milestone (delay) Forecasted Milestone (early)

  6. Deployment Update As of August 3, 2012

  7. 2012 Budget Status – Expenditures by Workstream Year-to-Date Variance Explanations: Favorable YTD capital variance ($25.1M) primarily due to fewer meter/module installations (#3), fewer electric meter purchases (#4), and delayed timing of initial HAN roll-out (#5). Favorable YTD expense variance ($5.6M) primarily due to lower spending than planned in Business Operations/PMO (#7), Customer (#10) and IT (#13). * Annual budgets revised with intent to complete project in 2013.

  8. 2012 Budget Status – Benefits

  9. Issues Summary

  10. Risks Summary

  11. Program Metrics

  12. Project Deployment Plan Progress

  13. Contingency Reconciliation

  14. SmartMeterTM Acronyms

More Related