Janet6 update
Download
1 / 15

Janet6 Update - PowerPoint PPT Presentation


  • 93 Views
  • Uploaded on

Janet6 Update. Neil Shewry Project Manager. Agenda. Background Procurement What we’re building How we’re getting on Strategic Research Facilities Plans for the future. Background. SuperJanet5: 2006 to 2013. Janet6: Project to replace the UK wide Janet backbone, SuperJanet5.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Janet6 Update' - alyssa-edwards


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Janet6 update

Janet6 Update

Neil Shewry

Project Manager


Agenda

Agenda

  • Background

  • Procurement

  • What we’re building

  • How we’re getting on

  • Strategic Research Facilities

  • Plans for the future


Background

Background

SuperJanet5: 2006 to 2013

  • Janet6: Project to replace the UK wide Janet backbone, SuperJanet5


Procurement

Procurement

  • Fibre infrastructure contract signed: 31st July 2012

    • Scottish & Southern Energy Telecoms (SSET)

    • 4 year framework

    • 10 (+5) year contract

    • £30M

  • Optical transmission contract signed: 6th September 2012

    • Ciena Inc.

    • 7 year framework

    • Order for supply and 5 years support

    • £12.8M


  • What we re building

    What we’re building

    • 5 delivery phases

    • Core

    • 4 Regional

    • RNs connect at multiples of 10G

    • Most are getting an upgrade


    What we re building1

    What we’re building

    I could go into more detail…

    …but how good is your eyesight?


    What we re building points of presence

    What we’re building - Points of Presence

    • Vacating the Verizon Business PoPs

      • Except for small presence in Glasgow and Reading

    • Existing Provider-Neutral PoPs

      • Telehouse North, Telecity Harbour Exchange

      • Telecity Manchester, Scolocate

    • New Provider-Neutral PoPs

      • Telecity Powergate, Telehouse West, Leeds (aql)

    • SSET Core PoPs

      • Bradley Stoke, Erdington, Lowdham, Glasgow

    • SSET Transmission PoPs

      • Multiplex circuits from regional fibres onto the backbone

    • SSET In-Line Amplifier PoPs

      • Single rack, small amplifier shelf

    • RNEPs


    What we re building lightpath

    What we’re building - Lightpath

    • Increase bandwidth between backbone nodes to 100GE

    • Topology reflects what is currently required


    How we re getting on fibre

    How we’re getting on – fibre

    • Acceptance of core infrastructure February 2013

    • Acceptance of regional infrastructure March 2013


    How we re getting on dwdm equipment

    How we’re getting on – DWDM equipment

    • Ciena 6500 platform

    • All kit is in the country

      • 40% on site

      • 60% in staging

    • Deployment began in January

      • Staging

      • Delivery

      • Installation

      • Commissioning

    • Completion end April 2013


    How we re getting on ip routing equipment

    How we’re getting on – IP routing equipment

    • Upgrade: Juniper T1600 Juniper T4000

    • Professional Services


    How we re getting on other stuff

    How we’re getting on – other stuff

    • Regional Network Readiness

      • Space & power

      • RNEP router capability

    • Transition Planning

    • Operational Readiness

      • PoP Control

      • Fault Management

      • Network Management

    • Service Management

      • SSET

      • Ciena

    • Decommissioning


    Strategic research facilities

    Strategic Research Facilities

    • Government e-Infrastructure initiative

      • £26m funding to Janet

        • £10m for Janet6 backbone

        • £12m for phase 1 (below)

        • £4m for ‘industrial connectivity’

    • Phase 1

      • Met Office, Exeter

      • Norwich Research Park

      • Hinxton Campus, Cambridge

      • (Francis Crick Institute, St Pancras)


    Plans for the future

    Plans for the future

    • LOTS of bandwidth

      • 100Gbit/s x 88 channels = 8.8Tbit/s

      • 400Gbit/s?

    • Strategic Research Facilities – possible phase 2

    • Thames Valley Network

    • South Region (formerly LeNSE)

    • Other regional networks?

    • Individual customers?