DC Tie Automation Project

DC Tie Automation Project. Automation Project Objectives. Automate Comparison of eTags to QSE DC Tie Schedules Automate Operator offsets for DC Tie eTag/Schedule mismatches Monitor/compare eTag Net Scheduled Interchange to DC Tie SCADA on EMS Display Automate Inadvertent Energy Accounting.

alva
Download Presentation

DC Tie Automation Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DC Tie Automation Project

  2. Automation Project Objectives • Automate Comparison of eTags to QSE DC Tie Schedules • Automate Operator offsets for DC Tie eTag/Schedule mismatches • Monitor/compare eTag Net Scheduled Interchange to DC Tie SCADA on EMS Display • Automate Inadvertent Energy Accounting

  3. Automate Comparison of eTags to QSE DC Tie Schedules • Add a QSE number or drop down tab in eTag form to Identify ERCOT QSE • Upload ERCOT DC Tie schedules to OATI • Contract with OATI for new displays to sort and compare eTags to QSE DC Tie schedules • Download eTag schedule data from OATI to MDB and Settlements • Enhanced eTag/QSE Schedule reporting capability

  4. Automate Operator offsets for DC Tie eTag/Schedule mismatches • Download approved eTag schedules to ERCOT MDB and MOS • Substitute eTag Schedules for QSE DC Tie Schedules in the operating period real time applications • Automatically provides correct DC Tie flow to SPD for congestion analysis and balancing • Manual operator offset for DC Tie mismatches no longer necessary

  5. Monitor/Compare eTag Net Scheduled Interchange to DC Tie SCADA on EMS Display • Sum of eTags for DC Tie equals Net Scheduled Interchange • NSI downloaded from OATI and linked to an EMS display next to DC Tie SCADA value • Alarm for Differences • Errors identified quickly

  6. Automate Inadvertent Energy Accounting • Perform Inadvertent Energy Accounting on OATI application • Eliminate internal manual spreadsheets • Upload EPS meter data for DC Ties for final meter reading corrections • Inadvertent Energy information downloaded from OATI for final archives • Enhanced OATI reporting capabilities