An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HT-7实验诊断系统准备 2012-09-06

  2. 远红外系统(完成)

  3. ECE系统 • 16道ECE外差系统已经从EAST大厅搬至HT7大厅。 • 已完成波导架设及系统的搭建工作 • 已将16道ECE输出信号端接至7室采集端 • 初步完成系统测试工作,噪声管定标正在进行中。 • HT7实验准备工作基本完成(等待和总控联调)。

  4. 光谱系统 Da (HA1-35 )(完成安装) CIII (VIS1-9)(完成安装) Bremstrahlung Emission (VB1-3) (完成安装) OII /LiI/LiiI(完成安装) MoI/DA各一道(待安装) 各光谱系统等待和总控联调!

  5. 高分辨率汤姆逊散射诊断系统(完成) • 8.13-19 系统硬件平台搭建  • 准备激光器(把激光器搬移到老激光房,连接电源,换制冷水等) • 准备侧窗口,搭建散射信号收集系统,安装调试收集透镜,光纤等 • 准备TV系统,维修(购置)高压电源模块变压器, • 连接网络系统(触发、采集、反馈和控制网络) 激光器 侧窗口 换冷却水

  6. 8.20-26 系统台面调试 • 调试激光器,测试能量、光束质量和光斑形状等参数 • 测试倍频系统,倍频效率调节 • 查询、检测各信号线 • 清洁下窗口,光路调节 下窗口 下窗口清洁

  7. 8.27-9.4系统联调 • 根据实验情况及出现的问题进行调试 • 系统联调,触发、时序、门参数调节测试 • 目前,已完成系统硬件准备工作 门时刻调节后,杂散光测试

  8. 核测量组各诊断系统 • 软X射线阵列:水平窗口一个阵列,35道 • 软X射线能谱:垂直窗口一个阵列,10道 • 硬X射线:垂直窗口一个阵列,10道 • AXUV:水平窗口一个阵列,16道 • 中子:装了2个探测器 • 所有诊断都安装到位,下一步将和总控、采集进行联调。

  9. 可见视频诊断系统 高速可见视频系统安装于南窗口,目前系统工作正常,由于用于光路测试的高速相机尚未到,目前还未进行系统联调,预计能在本周内完成所有测试。

  10. 谢 谢!