An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Module 3 Dr. Mohamed Zamil AL-Akhtaby

  2. Network Computation Process • Forward Pass—Earliest Times • How soon can the activity start? (early start—ES) • How soon can the activity finish? (early finish—EF) • How soon can the project finish? (expected time—ET) • Backward Pass—Latest Times • How late can the activity start? (late start—LS) • How late can the activity finish? (late finish—LF) • Which activities represent the critical path? CP • How long can it be delayed? (slack or float—SL)

  3. Gantt chart General Foundry project A B C D E F G H Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Week Budgeting for General Foundry

  4. Budgeting for General Foundry • Activity costs for General Foundry

  5. General Foundry Example • Normal and crash data for General Foundry

  6. General Foundry - QM

  7. After crashing the project by 1 week, this is the new network Two critical paths A-C-E-G-H B-D-G-H Revised Path After Crashing • Two critical paths • A-C-E-G-H

  8. RESOURCE MANAGEMENT - LOADING & LEVELING What is a resource? Resource is a generic word and is used in various ways.  For our discussion, we would restrict it to 4Ms or Man, Machine, Material and Money. What is management? Once again, Management is a generic word.  To simplify, it is a process of planning, implementing and controlling the resources to achieve desired objectives.

  9. RESOURCE MANAGEMENT - LOADING & LEVELING What is resource management? Resource Management is using resources efficiently and effectively. To sum up, efficiency is having more output for the same input or less input for the same output. What are Resource Management Techniques? When we come to techniques, we would once again restrict ourselves to: Resource Loading and Resource Leveling as follows:

  10. RESOURCE MANAGEMENT - LOADING & LEVELING

  11. RESOURCE LEVELING

  12. RESOURCE LEVELING

  13. RESOURCE LEVELING

  14. RESOURCE LOADING

  15. RESOURCE LOADING

  16. RESOURCE LOADING

  17. RESOURCE LOADING

  18. RESOURCE LOADING

  19. RESOURCE LOADING

  20. Dependency (project management)

  21. Dependency (project management)

  22. Resources loading and resources leveling

  23. Thank you Email for Questions