1 / 6

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid. N. Delruelle on behalf of the TE/CRG group LS1 Infrastructure Meeting – 16 Apr 2014. Outline. layout of the new supply 10’000 litre LHe dewar Interconnecting valve box

aleta
Download Presentation

ATLAS LS1 infrastructure: Installation of a new 10’000 litre LHe dewar for the Solenoid

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS LS1 infrastructure: Installation of a new 10’000 litreLHedewar for the Solenoid N. Delruelleon behalf of the TE/CRG groupLS1 Infrastructure Meeting – 16 Apr 2014

  2. Outline • layout of the new supply • 10’000 litre LHedewar • Interconnecting valve box • 2 Transfer Lines TL4 and TL5 • Planning of the new supply • Manufacture • Integration in UX15

  3. Layout of the new supply Existingtransfer line TL2 New transfer line TL4 New 10’000 L dewar Existingtransfer line TL1 New valve box New transfer line TL5 Courtesy of Jos Metselaar

  4. Layout of the new supply Existingtransfer line TL2 New transfer line TL4 New 10’000 L dewar Existingtransfer line TL3 to solenoid New valve box Courtesy of Jos Metselaar

  5. Manufacture planning • The valve box: • Manufacturing: by week 12/201418/2014 • Test of the electrical cabinet: by week 14/201418/2014 • Transfer lines TL4 & TL5: • Manufacturing: by week 10/2014 ˅ • The 10’000 litre LHedewar: • Manufacturing inner & outer vessel: by week 5/201416/2014 • Insulation: by week 7/201418/2014 • Inner plumbing: by week 10/201421/2014 • Test of the electrical cabinet: by week 10/201422/2014

  6. Installation planning in Point 1 • The valve box: • Installation: week 20/2014 (12 May) • Transfer lines TL5: • Installation: fromweek 20 to week 23/2014 (from 12 May to06 June) • Leak test on TL5: week 24/2014 (09 June) • The 10’000 litre LHedewar & TL4: • Handling & Installation: week 24/2014 (09 June) • Connection between dewar and TL4: week 25/2014 (16 June) • Leak test on TL4: week 26/2014 (23 June) • Cutting & connection to existing TL3: from week 27 toweek 29/2014 (from 01 July to 18 July)

More Related