Case Study Water and Waste Water Infrastructure Northern Ireland Martin Darcy United Kingdom

Case Study Water and Waste Water Infrastructure Northern Ireland Martin Darcy United Kingdom. « Concessions and Public- Private Partnerships  » Ankara, 10-11 March 2008. Drivers. EU Directives Scale of overall investment needs Water reform and lack of internal implementing resource

aleake
Download Presentation

Case Study Water and Waste Water Infrastructure Northern Ireland Martin Darcy United Kingdom

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case StudyWater and Waste Water Infrastructure Northern Ireland Martin DarcyUnited Kingdom « Concessions and Public-PrivatePartnerships »Ankara, 10-11 March 2008

  2. Drivers • EU Directives • Scale of overall investment needs • Water reform and lack of internal implementing resource • Strategic Investment Board (SIB)

  3. Options • Mix of public and private sector investment • New build or renovate • Greenfield or existing sites • Low technology or new technology

  4. Preferred Solution • Publicly financed investment only to the credible limit of the public sector’s ability to implement effectively • Private sector investment would deliver the rest - estimated at €350m of €1.4bn total • Private sector investment programme (PPP Programme) broken into two major multi-site procurements: • Drinking Water projects – named ‘Project Alpha’ • Waste Water projects – named ‘Project Omega’

  5. Project Alpha - Objectives • To provide 50% of Northern Ireland’s drinking water capacity • To achieve quality standards compliant with EU Drinking Water Directive • To achieve the above to meet legal deadline

  6. Water Treatment – Project Alpha • 5 Existing sites • Estimated €200m of investment • No land acquisition issues • Few planning difficulties anticipated • Relatively straight forward contract structure • One procurement process for all five

  7. Water Treatment Issues – Project Alpha • The most attractive and bankable structure had ‘balance sheet’ issues; this led to a major crisis of confidence amongst some stakeholders • Raw water data • Raw water consistency • Sludge management

  8. Preparation, Procurement and Initiation– Project Alpha • May 2003 – Inception • January 2004 – Project Launch • May 2004 – Call for competition • May 2006 – Financial Close (ahead of schedule by 3 months) • March 2008 – construction work almost complete and ahead of schedule

  9. Outcomes – Project Alpha • Winning bid = €70m capital cost saving over initial engineers estimates • Whole life savings of 19% • Project procured 3 months ahead of schedule • Claimed by the advisers to be a ‘World Record’ time for a major infrastructure financing

  10. Waste Water – Project Omega • Renovation / new build and rationalisation with investment requirement estimated at €150m • Three key geographical areas • One procurement process for all three areas • Rationalisation element gave great scope for innovation • No preconceptions about which technical solutions to use • Several bankable templates already in existence

  11. Project Omega Issues during Preparation Stage • Sludge management • Trade effluents • Infiltrations • Flow and Composition base data • Planning issues concerning some sites • Land acquisition required on at least one site

  12. Project OmegaIssues During Procurement Stage • Urgent investment need requiring an Advance Works Contract – high risk strategy for Authority • Reform of the Northern Ireland Water Service – ‘the Authority’ • The sale of the Preferred Bidder to a private equity consortium • Inadequate leadership from senior management at Preferred Bidder

  13. Project Omega – Key timings • Advisers appointed January 2004 • OJEU December ’04 • Preferred Bidder appointed January ‘06 • Financial Close March ’07 • Construction almost complete – on schedule

  14. Project Omega – Outcomes • Project signed one month later than forecast • 11% improvement in whole life vfm compared to the Public Sector Comparator • Construction on Schedule • Represented the successful conclusion of a major PPP Programme

  15. Main Lesson Learned on the Entire Programme • Investment in thorough evaluation and good preparation pays back through good results in: • On time delivery • Value for money • Avoidance of legal challenges