Ssr1 cryomodule design and fabrication schedule
This presentation is the property of its rightful owner.
Sponsored Links
1 / 5

SSR1 Cryomodule Design and Fabrication Schedule PowerPoint PPT Presentation


  • 259 Views
  • Uploaded on
  • Presentation posted in: General

SSR1 Cryomodule Design and Fabrication Schedule. Tom Nicol - Fermilab. Design and Fabrication Schedule From July 2011. Front End Test Facility Planning SSR0 prototype cryomodule development/fabrication branch Possible schedule Systems integrated in the cryomodule Cryosystem SRF cavity

Download Presentation

SSR1 Cryomodule Design and Fabrication Schedule

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Ssr1 cryomodule design and fabrication schedule

SSR1 Cryomodule Design and Fabrication Schedule

Tom Nicol - Fermilab


Design and fabrication schedule from july 2011

Design and Fabrication ScheduleFrom July 2011

PXIE Cryomodule Design Meeting

Front End Test Facility Planning

SSR0 prototype cryomodule development/fabrication branch

Possible schedule

Systems integrated in the cryomodule

Cryosystem

SRF cavity

Power coupler

Tuner

Focusing lens

Alignment

TNicol

Assume:Dressed cavities are available as-needed.

2 identical cryomodules with 9-10 cavities each.

Engineering, design, drafting, and production resources available

as-needed.

October 2016Production cryomodules ready for installation and testing.

October 2014Production cryomodule parts in-house (not including cavities).

October 2013Production cryomodule parts ordered.

June 2013Production cryomodule design complete.

May 2017Prototype cryomodule is ready for installation in the beamline.

Nov. 2015Cryovessel is delivered to FNAL. Cryomodule assembly components are in house. Cryomodule assembly starts.

Feb. 2014Cryovessel order is placed.

Oct. 2013 Cryovessel design is complete.


Design and fabrication schedule from july 20111

Design and Fabrication ScheduleFrom July 2011

PXIE Cryomodule Design Meeting

November 201610 SSR0 ready for cryomodule assembly

November 2015SSR0 jacketed cavity tests start in cryostat

August 2015SSR0 Jacketing starts

June 2015SSR0 VTS testing starts

March 2015SSR0 processing starts

Dec 2014SSR0 order is received

April 2014SSR0 Production order is placed (~12 cavities)

January 2014Prototype SSR0 cavity is jacketed and is tested in cryostat. Design modification period starts.

June 2013SSR0 prototype cavity is processed / VTS-tested.

Dec 2012SSR0 Prototype cavity is received

Dec. 2011SSR0 prototype cavity order is placed.

June. 2016Couplers are ready for installation

Dec. 2015Production couples test and processing start

Dec. 2014Order is placed for SSR0 production coupler fabrication

Dec. 2013Prototype coupler is tested. Design modification period starts.

Nov. 2012Prototype coupler is ordered

Dec. 2011Power coupler design is complete


Design and fabrication schedule from july 20112

Design and Fabrication ScheduleFrom July 2011

PXIE Cryomodule Design Meeting

January 2015Production tuners are ready for installation

March 2014Production tuner order is placed

Dec. 2013Prototype tuner is tested with a prototype cavity

Nov . 2011Tuner concept is finalized

Dec. 2014Focusing lens assemblies delivered to the cryomodule assembly site.

March 2014Order is placed for production focusing lens fabrication

Nov. 2013Prototype focusing lens is tested. Design modification period starts.

July 2013Prototype SSR0 lens is tested. Design modifications start.

May 2013Prototype lens fabrication starts.

Oct. 2012SSR0 lens design is complete

Sept. 2012Focusing lens design is complete

May 2012Lens concept is proposed

March 2012 Lens fringe magnetic field requirement is finalized

Dec. 2011Lens cooling scheme is finalized

Oct. 2011Quench protection solution is found

Dec 2014Alignment procedures and techniques are finalized. Equipment procurement starts

June 2013Long base alignment test is made; Alignment system design starts

Nov. 2011Alignment study for the SSR0 cryomodule is complete


Design and fabrication schedule

Design and Fabrication Schedule

PXIE Cryomodule Design Meeting

  • Assume:

    • Dressed cavities are available as-needed.

    • 1 SSR1 cryomodule with 8 cavities, 4 solenoids.

    • Engineering, design, drafting, and production resources availableas-needed.

  • June 2013Production cryomodule design complete.

  • October 2013Production cryomodule parts ordered.

  • October 2014Production cryomodule parts in-house (not including cavities).

  • October 2016Production cryomodules ready for installation and testing.


  • Login