An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SA AIR FORCE PRESENTATION TO THE PORTFOLIO COMMITTEE ON DEFENCE 17 NOVEMBER 2010 Brig Gen W.S. Mbambo Director Air Capability Plan

  2. Scope • Introduction • Strategic Objectives for the FY09/10 • Strategic Objectives Not Achieved • SAAF Achievements • SAAF Challenges & Mitigations • Conclusion

  3. Strategic Objectives for FY09/10 • Defend and protect South Africa and its airspace by: • Providing 4 helicopter squadrons and one combat support squadron a year; • Providing three medium transport squadrons, one maritime and transport squadron, one light transport squadron and nine reserve squadrons at the required readiness levels a year; • Providing one air combat squadron a year, and • Providing a 24 hour air command and control capability

  4. Introduction • SAAF mandate and allocation not aligned. • The delta implies hard decisions with serious implications. • SAAF uniqueness compounds the problem. • SAAF total allocation for FY 2009/10 was Rb 3,1: • Personnel: Rb 1,6 • Operations: Rb 1,5 • SAAF was under funded by: • Operations: Rm 132 4

  5. Strategic Objectives Not Achieved • Medium, Light & Combat Support Helicopter Capability: • Planned: 11 920 • Achieved: 10 431 • Reasons: . • Low availability of systems, due to funding shortages. Low experience levels of ground crew resulted in services taking longer to complete. Production errors on A109 fleet decreased availability. Ratio of Oryx commanders to co-pilots unbalanced with too few commanders.

  6. Strategic Objectives Not Achieved • Transport & Maritime Surveillance Capability: • Planned: 11 825 • Achieved: 11 179 • Reasons: • Scheduled and unscheduled maintenance activities, technical failures, accidents, a lightning strike, long lead times on spares and insufficient technical personnel to maintain required servicing schedules. Financial constraints on some maintenance activities. • NB: The very old age factor in some of the aircraft within this capability severely impacts on serviceability & availability.

  7. Strategic Objectives Not Achieved • Air Combat Capability: • Planned: 950 • Achieved: 715 • Reasons: • Substantial under funding of systems. Long lead-times on spares. Gripen support package has not been fully delivered. Major software upgrade was performed to ensure all aircraft are on same modification baseline. Software upgrades on Hawk affected availability. Long turn around time of components in repair loop. • NB: With the Hawk system getting out of warranty service contractual arrangement, the situation will get worse in the current & future years.

  8. SAAF Achievements • 32866 Flying hours were achieved with one major aircraft accident (A109). • The Air Force continues to make maximum use of Reserve Force aircraft in lieu of chartering civilian aircraft, which is a much more expensive option . • 26 pilots qualified for wings. • Transport & Maritime – 11. • Helicopters – 10. • Combat – 5.

  9. SAAF Achievements • Hawk squadron fully operational for combat training. • Main runway at AFB WKLF upgraded, nearly all operations resumed. • Commercialisation of SAAF messes resulting in savings for the SAAF. • The first ATNS training within SAAF, contributing towards resolving ATC’s shortages. • Successful CASEVAC and Search and Rescue operations assisting other departments

  10. SAAF Challenges & Mitigation Scarce Skills: Interaction with aviation industry & other relevant stakeholders • Scarce skills is both a national & global challenge • Aviation technical training in the country • SAAF – Denel Aviation cooperation activities to eliminate duplication and reduce costs • SAAF & South African Airways discussions on common challenges. • SAAF & Air Traffic and Navigation System (ATNS) interaction on common challenges.

  11. SAAF Challenges & Mitigations • Combat system in the balance, will require intervention to prevent loss of the required capability. • Due to inadequate funding of the Hawk and Gripen systems since the onset of integration, the Air Force has not been able to generate the required number of flying hours and re-provision the systems adequately. • Intervention (short term) • Download Hawk hours to Pilatus (under investigation) • Fly Gripen at minimum to maintain system integrity & to maintain competencies only. • Utilisation of simulators.

  12. SAAF Challenges & Mitigations • Relocation of AFB Durban to King Shaka International Airport (KSIA). • Short Term: Utilise current location for rotary operations. Use KSIA for fixed wing air transport. • Rm 27.2 is required to replace temporary buildings at AFB Durban in order to sustain Rotary Wing Operations. • Long Term: Total relocate base and domestic facilities to KSIA at a cost of Rm 729. SAAF has no funds. • Intervention • SAAF continually raise its operational requirements through the DOD, NDPW and other stakeholders.

  13. SAAF Challenges & Mitigations • Fund upgradesfrom Capital and not operating funds. • In the past some upgrades have been partially funded from the operating budget, eg Project DRUMMER (Oryx mid-life upgrade) where the provision on the capital budget was inadequate. • Future thinking wrt digital technology maintenance philosophy (continuous upgrades from capital)

  14. SAAF Challenges & Mitigations • Impact of Low Funding Levels. • Low flying rate. • Support to Operations. • Force Preparation (SAAF and other Services). • Retention and representativity improvement affected. • Inappropriate balance between capabilities. • Intervention • More utilisation of simulators • Discussions & agreements with SAA and other local airlines

  15. SAAF Challenges & Mitigations • Command & Control Capabilities • Radar Systems & associated mobile equipment old. • SAAF communications network infrastructure. • Mobile Air Operations Team (MAOT) support capabilities not guaranteed. • Intervention • Strategic Capital Acquisition Master Plan (SCAMP ) reprioritisation.

  16. Conclusion • SAAF has a unique mandate viz. Air Defence of the RSA • SAAF has valuable assets in SDP’s with proven track record so far [Confederations Cup & recent FIFA SWC] • Any system integrity loss from the SDP’s would result into more serious problems & expenses. • A fair balance between mandate and allocation needs to be found.

  17. Questions…