g2p/ gEP Beamline Status

g2p/ gEP Beamline Status. 8/30/11. Mechanical Systems. Region 1: All design work complete, material procured, installed, and pumped down. SR PS bunker/cooling blower to be assembled within a week. Region 2: Harp alignment/installation into upside down girder.

alaric
Download Presentation

g2p/ gEP Beamline Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. g2p/gEP Beamline Status 8/30/11

  2. Mechanical Systems • Region 1: • All design work complete, material procured, installed, and pumped down. • SR PS bunker/cooling blower to be assembled within a week. • Region 2: • Harp alignment/installation into upside down girder. • Upside down girder installation expected within the week. • Region 3: • FZ1 and FZ2 stands and magnets are installed. • All arm/girder material has been designed and all but a couple of components which support the arms has been ordered and scheduled for delivery by the end of September. • Assembly of FZ2 arms, viewer girder, and downstream diagnostics girder remain – scheduled for early October. • Final 2B alignment planned for mid October.

  3. 8-30-11 LA D-T FZ#2 Motion Mechanism Trunion & Arms U/S & D/S Due: 9/20/11 Upstream Girder Due: 9/22/11 Downstream Girder, Lead Screw, Elevator (Bearings, Lead Screw & Nut) & Plate . Due: Camera Holder Due: TBD Downstream Girder Guides Due: 9/12/11 Upstream and Downstream Arm Support, Elevator (Bearings, Lead Screw & Nut, Guides & Plate.) Due:~ 10/5/11

  4. Electrical Systems • Region 1: • Calorimeter installed and tested. Final calibration in September. • SR will have final hookup and test in September – already verified performance and new control scheme in the lab. • Region 2: • Once the upside down girder is installed, all diagnostics and vacuum monitoring must be connected and proven. • Compton upgrade/repair completion is questionable. • Harp controller chassis SW is the long pole in the tent. • Region 3: • FZ1 and FZ2 magnet magnets are installed and connected. • Once diagnostics are installed in early October, they must be connected and tested. Low risk. • Desire to test FZ magnets sooner than later, LCW may push this out until late September.

  5. Electrical Systems – cont’d • BPM/BCM Receiver: • Functioning on the bench; will require a re-spin of the board – due mid-September. • FW complete and functioning. • SW complete and functioning. • Will require an off board oscillator for BPM calibration. • Harp Controller: • Board and chassis completely assembled. • Will reuse as much FW as possible; should reduce required time to complete. • Reuse/standardization to existing harp SW commands should reduce required SW programming time. • Long pole in the tent; critical resource in I&C (Chad Seaton). • BPM Transport Modules: • On track for complete build, test, installation by end of September.

  6. Areas of Focus • Tracking mechanical component delivery, assembly, installation. • Testing of DC power supplies and FZ magnets. • Completion of the Harp Controller and BPM/BCM receiver. • Completion of all required SW and control screens. • Return to Operations documentation – Yves Roblin and Eric Forman • No Show Stoppers!