XRT Team Meeting

XRT Team Meeting. Location: ISAC/ASDC September 17-18, 2003. XRT Activation. Very limited command time during first week 3 orbits on Day 3 Minimal availability for rest of first week Minimal turnon and checkout during this period Checkout period before doors open

akina
Download Presentation

XRT Team Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. XRT Team Meeting Location: ISAC/ASDC September 17-18, 2003 XRT Team Meeting – ASDC – September17-18, 2003 (Page 1)

  2. XRT Activation • Very limited command time during first week • 3 orbits on Day 3 • Minimal availability for rest of first week • Minimal turnon and checkout during this period • Checkout period before doors open • Slow, methodical checkout of instrument • Leave plenty of time for thorough verification of telemetry • Leave time for dealing with any anomalies • Doors open ~ L+21, things get much busier! • Checkout ends about 4 weeks after launch, followed by calibration XRT Team Meeting – ASDC – September17-18, 2003 (Page 2)

  3. XRT Activation Sequence(XRT-PSU-056) • Day L+3: power on, initial tests, vent camera • Orbit N • Turn on power, monitor HK and self-test • Switch HK to TDRSS, monitor for one orbit • Orbit N+1 • XRT aliveness test: verify 1553, command and telemetry interfaces • Verify RAD6000 memory status • Orbit N+2 • Turn on mirror baffle heaters • Warm CCD to +30C (for 120 minutes) • Orbit N+3 • Open FPCA vent for 10 minutes • Open Sun Shutter (should already be open) • Take one raw CCD frame (verify detector) XRT Team Meeting – ASDC – September17-18, 2003 (Page 3)

  4. XRT Activation Sequence(XRT-PSU-056) • Day L+4,5,…,21: vent camera • Orbit N • Warm CCD to +30C (for 120 minutes) • Orbit N+1 • Open FPCA vent for 10 minutes • Orbit N+2 • Take one raw CCD frame (verify detector) • Day 9: start checkout, verify TAM • Orbit N • Turn on TAM, test with both LEDs (full-frame images) • Day 10: start TAM data, turn on tube heaters • Orbit N • Begin taking TAM images every 5 minutes • Orbit N+1 • Verify TAM window images • Orbit N+2 • Turn on tube heaters • Orbit N+3 • Monitor tube heater operation and TAM centroid behavior XRT Team Meeting – ASDC – September17-18, 2003 (Page 4)

  5. XRT Activation Sequence(XRT-PSU-056) • Day 11: check noise on signal chains • Orbit N • Take 3 raw frames, high gain, A side, serial clocks backwards • Verify amp/signal chain, measure noise • Orbit N+1 • Take 3 raw frames, low gain, B side, serial clocks backwards • Verify amp/signal chain, measure noise • Day 12: check camera functionality • Orbit N • Take 5 raw frames, high gain, A side, all clocks forwards • Verify amp/signal chain, measure noise • Orbit N+1 • Take 5 raw frames, low gain, B side, all clocks forwards • Verify amp/signal chain, measure noise XRT Team Meeting – ASDC – September17-18, 2003 (Page 5)

  6. XRT Activation Sequence(XRT-PSU-056) • Day 13: verify filter integrity • Orbit N • Turn on FPCA LED, take raw frame, verify filter integrity • Q: do we want A and B sides? • Day 14: Cool CCD, check camera noise, energy resolution • Orbit N • Cool CCD to –100 C • Orbit N+1 • Take 5 raw frames, high gain, A side, all clocks forwards • Verify amp/signal chain, measure noise • Orbit N+2 • Take 5 raw frames, low gain, B side, all clocks forwards • Verify amp/signal chain, measure noise XRT Team Meeting – ASDC – September17-18, 2003 (Page 6)

  7. XRT Activation Sequence(XRT-PSU-056) • Day 15: check all readout modes • Orbit N • Collect 5 PuPD mode frames • Measure noise, gain, FWHM • Orbit N+2 • Collect 100 LrPD frames • Measure gain, FWHM • Orbit N+3 • Collect bias row • Collect 500 WT frames • Measure gain, FWHM • Orbit N+4 • Collect bias map • Collect 200 PC frames • Measure gain, FWHM XRT Team Meeting – ASDC – September17-18, 2003 (Page 7)

  8. XRT Activation Sequence(XRT-PSU-056) • Day 16: SAA tests • Collect one raw frame per minute during SAA passages to map out SAA • Day 17: Open XRT telescope door • Orbit N: open telescope door • Orbits N+2, N+3: collect some CCD data (raw frames) • Orbit ?: collect PuPD and IM data in SAA • L+18: Collect calibration data in LrPD mode • Run camera in LrPD mode for one day • L+19: Collect calibration data in WT mode • Run camera in WT mode for one day • L+20: Collect calibration data in PC mode • Run camera in PC mode for one day XRT Team Meeting – ASDC – September17-18, 2003 (Page 8)

  9. XRT Activation Sequence(XRT-PSU-056) • Day 21: Open FPCA door • Orbit N • Turn off TEC • Orbit N+1 • Warm CCD to +30 C • Begin venting camera (throughout orbit) • Orbit N+2 • Continue venting camera • Open FPCA door • Orbit N+4 • Turn off TEC, let CCD cool down to cold finger temp • Orbit N+5 • Check filter integrity XRT Team Meeting – ASDC – September17-18, 2003 (Page 9)

  10. XRT Activation Sequence(XRT-PSU-056) • Day 22: Cold Tests (or first light? What order do we want to do?) • Orbit N • Cool CCD to –100 C • Orbit N+1 • Collect 5 (TBR) raw high gain frames on Amp A [focus check] • Is 5 frames sufficient? • What is appropriate target? • Point source? {for focus check} • How bright? • Orbit N+2 • Collect 5 raw low gain frames on Amp B • Same questions • Orbit N+3 • Collect 5 frames in PuPD mode • Needs point source. Can we do anything with 5 frames? • Orbit N+4 • Collect 100 frames in LrPD mode • Is this enough frames (only about 820 seconds exposure)? • Point source or Crab? XRT Team Meeting – ASDC – September17-18, 2003 (Page 10)

  11. XRT Activation Sequence(XRT-PSU-056) • Day 22 (cont.) • Orbit N+5 • Collect bias row • Collect 500 WT frames • Measure FWHM and gain (how??) • Orbit N+6 • Collect bias map • Collect 200 PC frames • Measure FWHM and gain • Day 23: Centroiding tests • Orbit N • Collect 100 short image frames, verify centroiding • Orbit N+1 • Collect 100 long image frames, verify centroiding XRT Team Meeting – ASDC – September17-18, 2003 (Page 11)

  12. XRT Activation Sequence(XRT-PSU-056) • Day 24: Test Auto State, collect bias information • Orbit N • Slew to bright targets (e.g. Sco X-1, Crab, etc.) as ATs • Verify correct XRT mode switching • Verify TDRSS messages • Orbit N+1 …. • Switch to Manual state • Point at blank sky • Collect bias information for IM mode for one day (one frame every 15 minutes) • May want to collect PD every minute for one orbit, let other instruments select targets for rest of day. • Day 25: WT mode bias tests • All orbits • Manual state • Point at blank sky • Collect bias rows • Collect 1000 WT frames • Repeat for one day XRT Team Meeting – ASDC – September17-18, 2003 (Page 12)

  13. XRT Activation Sequence(XRT-PSU-056) • Day 26: Photodiode mode bias measurements • All orbits • Manual state • Point at blank sky • Collect PuPD frame • Collect 100 LrPD frames • Repeat for one day • NOTE: this may saturate telemetry capability for this day • Alternatively, use same strategy suggested above for IM mode. • Day 27: PC mode bias measurements • All orbits • Point at blank sky • Collect bias map • Collect 400 PC frames • Repeat for one day • Note: this could be done in either manual or auto state • Alternatively, use same strategy suggested above for IM mode. XRT Team Meeting – ASDC – September17-18, 2003 (Page 13)

  14. XRT Activation Sequence(XRT-PSU-056) • Days 28-30 • Switch to Auto state • Monitor instrument performance during slew tests to interesting targets • Official First Light observations??? • Press conference observations?? XRT Team Meeting – ASDC – September17-18, 2003 (Page 14)

  15. Launch / Early Orbit support • Burden should be light for first three weeks (but still 24 hours) • Joe or I will be on call 24 hours – we need European support for 12:00 – 8:00 EST • Use this as training period for duty scientists • Need full support beginning around day 21 • Operators (PSU) • Hill • Burrows • Gendreau? • Duty Scientists • (training) • Analysts (remote) • Mori (PSU) • Morris (PSU) • Mukerjee (UL) • Abbey (UL) • Beardmore (UL) • Campana (OAB) • Moretti (OAB) • New hire (OAB) • Instrument Duty Scientists • (one week at PSU) • Hill • Mukerjee (UL) • Beardmore (UL) • Moretti (OAB) • New hire (OAB) XRT Team Meeting – ASDC – September17-18, 2003 (Page 15)

  16. XRT Status • Hardware – no changes • Software – Build 8.5 installed in August • Fixes problems identified in Build 8.4: • Fix for TDRSS messages being sent coming out of SAA for all targets • Improved CPU usage in Windowed Timing Mode • Bias information for LrPD Mode • Fix for PC Mode when using a Bad Pixel Map and Bias Map • Number of pixels >LLD and <ULD corrected in Image Mode • Bias Map amp ID correction in data header • “SCUI not read event” telemetered even if data is not dropped • Residual issues: • Powering TAM on twice hangs TAM software • Workaround: kill TAM task and restart (also procs) • PuPD frame is still generated if we slew to target in SAA • Data rate is still about a factor of 2 too high (due to bias maps) • New Mode Sequence Table loaded • Removes PuPD frames from slews to reduce telemetry • Fix for TDRSS messages coming out of SAA XRT Team Meeting – ASDC – September17-18, 2003 (Page 16)

  17. Build 8.5 FSW upload Flight SW uploaded as part of SCIF#4a: • Flight procedures and flight STOL procs written for: • Full build upload to BC1 • Flight Software dump • Mode Sequence Table upload • Waveform upload • Test run from GSFC MOC • Included 3 hour wait between block #4 and #5 • FSW image dump to SSR • Rebooted from BC1 (in flight BC0 is locked) • MST upload • Waveform uploads • Instrument Aliveness performed through MOC XRT Team Meeting – ASDC – September17-18, 2003 (Page 17)

  18. Build 8.5 FSW testing/verification Tests performed post load: • Set boot index back to BC0 • CPT • DiTL • Plugs Out test • Ran S/C Emergency Power Down procedure Test Issues: • Powering the TAM twice ‘hangs’ the TAM SW • A PuPD frame is sent out when we come out of SAA, if we slew to a target while we are in the SAA XRT Team Meeting – ASDC – September17-18, 2003 (Page 18)

  19. DitL test Expand XRT Team Meeting – ASDC – September17-18, 2003 (Page 19)

  20. Settled SLEW SLEW SLEW SLEW In 10’ Bias Bias Bias DitL test SAA 8=Safe Hold 4=SAA 2=in 10’ 1=Settled 9=Bias 8=Raw 7=PC 6=WT 5=LRPD 4=PUPD 3=Long IM 2=Short IM 1=Null Bias PUPD Null LRPD XRT Team Meeting – ASDC – September17-18, 2003 (Page 20)

  21. Proposed additional FSW tests We plan to utilize the time made available by BAT slips to: • Test WT mode with 200 pixel window • Lock EEPROM • Verify new waveforms • Verify MST reload from EEPROM w/o reboot • Verify Bad Pixel Map and Bad Pixel Row • Verify SCUI buffer at 80 Mb • SAA test with observatory running new SAA polygon and XRT calculating its own SAA • Bad DiTL • Launch and Early Orbit Sims • Figure out baseline voltages for A low gain and B high gain XRT Team Meeting – ASDC – September17-18, 2003 (Page 21)

  22. Trending • Trending: what data do we need to trend? • Analog HK - MOC • TAM centroids - MOC • Corner source centroids and FWHM – SDC • Format: • ASCII table: easy to import into Excel • FITS: not clear to me how to handle this easily, esp. if in binary table format. XRT Team Meeting – ASDC – September17-18, 2003 (Page 22)