An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. eRA@Duke Project Update Office of Research Support Quarterly Grant Managers’ Meeting November 18, 2013

  2. Project Workstreams • Notice of Award • CAS/Rebudgeting • Fund Code & Plan Setup • Work has been slowed • Next steps being evaluated • Award Management & Closeout • Pre-planning groups assembled; work ongoing • Initial focus is on HHS, NIH Transition eRA@Duke 2013

  3. Notice of Award Go Live • Functionality Go Live: October 15, 2013 • October 15th:Letter announcing New PI Training disseminated • October 15th: SPS Web New Release* • January 6, 2014: Should required New PI Training not have been completed, Error will result when status is set to Awarded. Award will be held until Training has been completed • SPS Web Release* • Check applies to: PIs, Multiple PIs, Co-PIs, Mini PIs and PI-Fellows • RCC Email Notifications to be sent out from ORS/ORA [to initiator and person who needs to complete training] • New RCC Waiver Field for campus eRA@Duke 2013

  4. CAS/Rebudgeting Go Live • Pilot Go Live: October 31, 2013 • Full Rollout Go Live: targeted late January 2014 • CAS/Rebudgeting Functionality Highlights • CAS/Rebudget Form • Integration of SPS and SAP • Electronic routing and approvals improve process time • Automatic update of plan once approved by pre-award office • Automatic calculations and reduction of manual entry • CAS Report • Real time access to CAS data and potential non-compliance • Departments/Offices Participating in Pilot • ORA • ORS • OSP • RCC eRA@Duke 2013

  5. Questions? eRA@Duke 2013