1 / 28

LRFD Now!

LRFD Now!. Andy Zickler VDOT Structure and Bridge Division Central Office April 10, 2006 Andy.Zickler@VDOT.Virginia.gov. Status Update on LRFD Implementation . General Review of Implementation plan Training Plan Implementation Dates to Remember Review of Frequently Asked Questions

adeline
Download Presentation

LRFD Now!

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LRFD Now! Andy Zickler VDOT Structure and Bridge Division Central Office April 10, 2006 Andy.Zickler@VDOT.Virginia.gov

  2. Status Update on LRFD Implementation • General Review of Implementation plan • Training Plan • Implementation Dates to Remember • Review of Frequently Asked Questions • Information Exchange

  3. LRFD –Implementation Review • LRFD transition is historic • LRFD 1st mandatory change in design philosophy in bridge design in USA • ASD has been around since 1st AASHO Specification (1931) • LFD introduced in 1970’s but never mandatory for design across nation • LRFD mandated by FHWA for new bridge design beginning October 1, 2007

  4. Prepare! Prepare for Training Prepare for Design Prepare for Construction Train! Train for design Train for Specifications Train for Construction Implement! Issue new AASHTO Documentation Issue new VDOT Documentation DESIGN!!!! Follow UP! Provide Lessons Learned Check for other support needs LRFD –Implementation Review

  5. LRFD ImplementationPREPARE! • An LRFD Team has been named to design 2 complete bridges using LRFD • Team Members • Andy Zickler (Contact Person) • Tony Barati • Prasad Nallapaneni • John Schuler • Bryan Silvis

  6. LRFD ImplementationPREPARE! • LRFD team will be generating complete design computations on 2 bridges • One continuous steel bridge • One continuous P/S bulb tee Bridge • During the design process, team members will be reviewing all parts of the puzzle that make up the contract drawings and specifications

  7. LRFD ImplementationPREPARE! • VDOT contract elements will be reviewed for conformance with LRFD • Review will be 3 parts • Not impacted • Review complete with final recommendation for action • Review incomplete with preliminary assessment for action PLUS recommendation for further review.

  8. LRFD ImplementationTRAIN! • Train for Design • 3 Introductory 1 day training sessions • Structural Steel – Complete! • P/S Concrete Design – Complete! • Foundations – July, 2007 • 3 week long training Sessions (VDOT Only) • Superstructure Design – Taught by NHI • Software training – Taught by VDOT personnel • Substructure and Retaining Structures – Taught by NHI

  9. LRFD ImplementationTRAIN! • Train for Specifications • Structure of this training not determined, because extent of impact has not been determined. • Minimum will be self study. Changes to specifications will highlighted, and points of contact for questions will be distributed • Consultants will be advised of any VDOT Guidelines, preferences, etc.

  10. LRFD ImplementationTRAIN! • Train for Construction • Structure of this training not determined, because extent of impact has not been determined. • New specifications explicitly place responsibility for some items on contractor and outline specific requirements for submittal it is likely that we will see more P.E. stamped submittals for things like erection, deck placement, shipping. Learning what is required will be part of training at some point. • Consultants, Contractors, VTCA, etc. will be kept abreast of developments

  11. LRFD ImplementationIMPLEMENT! • Issue: • VDOT Modifications to LRFD Spec and/or Design Guidelines • Sample Problems and Design Aids • Revisions to VDOT Road and Bridge Standard Specifications (as necessary, if necessary) • Revised Standards, S&B Standard Drawings (as necessary, if necessary)

  12. LRFD ImplementationDESIGN!!!! • April 2, 2007 • Begin “all” designs using LRFD • Some widenings/rehabs may be excluded. * Definition of “all” to be determined based on what team finds and LRFD plans may change

  13. LRFD ImplementationFollow Up! • LRFD Team will not be disbanded on April 2, 2007 • LRFD Team will continue on for at least several months maybe until October, 2008 • LRFD team will help evaluate whether follow up class training will be required and will help establish parameters

  14. LRFD Trainingin Detail • 3 days of Introductory Training • (19.5 contact hours total) • Structural Steel – Complete! • P/S Concrete – Complete! • Foundations (July 11, July 12) • Classes will be lecture format • Classes will include consultant participants • Classes will only be offered on the dates shown, no repeats. • Classes will be in Richmond

  15. LRFD Trainingin Detail -- Software • Examples to be developed (FIRM) • 3 span straight steel plate girder • 4 span bulb-tee, continuous for LL • Concrete Multi-column pier (Rigid Frame Pier) • Concrete Hammerhead pier • Stub Abutment • Full Height Abutment • Wingwalls • Substructures will include piles and spread footings

  16. LRFD Trainingin Detail -- Software • Additional Examples (TENTATIVE) • Superstructure • Rolled beam • Continuous Conc. Slab • LAMPAD, Tooth • Substructure • Integral Abutment • MSE walls • Pile Bent

  17. LRFD Trainingin Detail -- Software • Additional Examples (TENTATIVE) • Others under consideration • Timber deck • Timber superstructure • Timber bents (pier and abutment) • Suggestions?

  18. LRFD --Dates to Remember • Dates through June, 2006 • March, 2006 Two one day seminars for steel superstructures • April, 2006 Two one day seminars for concrete super • 5/26 Issue preliminary report on LRFD Impactsto VDOT Modifications to AASHTO • 6/30 Complete 2 design projects • 6/30 Issue final report on LRFD Impacts to VDOT Modifications to AASHTO • 6/30 Issue preliminary report on LRFD Impacts to other VDOT Documents

  19. LRFD --Dates to Remember • Dates in July, 2006 • Issue LRFD Specs and Interims to engineers • 7/11 NHI one day seminar for substructure/foundations – Session 1 • 7/12 NHI one day seminar for substructure/foundations – Session 2 • 7/28 Issue final report on LRFD impacts to VDOT documents

  20. LRFD --Dates to Remember • Dates in August thru December, 2006 • 8/1 Issue preliminary Design Documentation on 2 design projects • 8/1-10/1 Release/review VDOT AASHTO Design Guides • 12/1 release 1st Ed. VDOT AASHTO LRFD Guides • Determine if additional training is required

  21. LRFD --Dates to Remember • Dates in January thru April, 2007 • 3/19 Planned LRFD Training complete. Evaluate whether additional training required. Develop plan if required • 3/30 Final reports on Standards/Office Practice • 4/2 Implement LRFD on all new bridge projects

  22. LRFD --Dates to Remember • Dates in May, 2007 and BEYOND • 5/25 Final report on VDOT specifications/special provisions • Support Software… • Provide support for implementation hiccups

  23. LRFD --Frequently Asked Questions • When is VDOT switching to LRFD? • What happens after the LRFD training? • When will I get my VDOT documents modified for LRFD Spec? • Will I have to design my next bridge in LRFD? • After the VDOT training, then what? Written Answers will be posted on Structure and Bridge LRFD page

  24. LRFD --Frequently Asked Questions (Con’t) • Who will answer LRFD questions when we start designing? • Where can I go to get more information on LRFD? Written Answers will be posted on Structure and Bridge LRFD page

  25. LRFD –Information Exchange • Keeping you informed – 3 ways • Structure and Bridge Division’s LRFD page atwww.virginiadot.org • Handouts from training, supplemental documentation • Have you tried it, does the LRFD site meet your needs? • Emails • Too many?, not enough?, right info?, wrong info? • VTCA • Updates to Executive Leadership • Coordination of consultant NHI Courses

  26. LRFD –Information Exchange • Getting information to the LRFD Team • Do you know how to get to us? • Phone (George Clendenin, Julius Volgyi, Andy Zickler) • Email (George Clendenin, Julius Volgyi, Andy Zickler) • Thru VTCA • Does this work for you? • Do you need a better way? • Do you have a better way?

  27. LRFD –Open Questions • What else do you want to know? • If we don’t know today when do you have to have an answer? • What did we leave out? • What information do you need to plan for your business? • When do you need it? • What form should it be in? • Anything else?

  28. LRFD Now! THANKS! Andy Zickler (804) 371-2776 VDOT Structure and Bridge Division Central Office April 10, 2006 Andy.Zickler@VDOT.Virginia.gov

More Related