![]() |
||||
Download Policy: Content on the Website is provided to you AS IS for your information and personal use only and may not be sold or licensed nor shared on other sites. SlideServe reserves the right to change this policy at anytime.
While downloading, If for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.
1. Port of Redwood City, CA
Marine Terminal Plan
2. Background and Need
3. Background and Need
4. Marine Terminal Plan Three-Phase Approach
Phase 1 – Completed October 3, 2005
Objective: Review cargo data and Port physical layout to determine the best use for Wharves 1 and 2 within the framework of the overall Port.
Phase 2 – Completed November 16, 2005
Objective: Develop an efficient, cost effective and constructible Marine Terminal Plan that responds to the best current and projected use identified for Wharves 1 and 2.
Phase 3 – Completed February 28, 2006
Objective: Further expand the Phase 2 conceptual plans and cost estimate and provide a plan for moving forward with the redevelopment project.
5. Marine Terminal Plan ELEMENTS OF THE PLAN
Wharf Redevelopment Plan
Demolition plan and recommendations
Interim Conveyor Plan – relocate ship receiving hopper away from cement berth
Site Development Plan
Raze Warehouse #1 and realign HS&G/CEMEX lease area to provide the Port with additional land for future development opportunities
Environmental and Permitting Review
Cost Estimates
Project Schedules
6. Wharf Redevelopment Plan Concrete pile supported concrete platform, 60’ wide x 490’ long (nominal)
500psf design deck load
Two approach trestles/ramps
Walkways between existing monopile fender dolphins
7. Wharf Redevelopment Plan Combination barge/ship fenders spaced along length of proposed wharf
Elevation to match existing timber wharf, slope access ramps to existing grade
Storm water runoff contained on wharf and directed to land along access ramps
Repair/replace landward seawall
8. Demolition Plan Recommend complete removal of existing timber wharf system
Overall, long term cost savings for demolition
Maintenance cost savings related to retaining deteriorating structures
Existing wharf stability is suspect, safety issues
Environmental benefit of removing old, creosote impregnated piles and deteriorating timber platform
9. Interim Conveyor Plan Relocate ship-unloading operations away from RMC/CEMEX
Demolition of Warehouse #1 NOT required
Realignment/modifications to HS&G/CEMEX yard NOT required
Low cost solution to help (partially) mitigate berth conflict issues
May initially utilize portable equipment on existing wharf, prior to reconstruction
Viable alternative for permanent system if HS&G/CEMEX does not realign yard
10. Preferred Marine Terminal Plan
11. Environmental & Permitting Review Bay Fill Mitigation Strategy (Demolition & Construction)
BCDC will require mitigation to offset any new construction
Removal off all existing structures are proposed to mitigate proposed construction; remainder will establish a mitigation bank
Can not lock in ratio of mitigation credit to new/proposed fill elsewhere in the Port
NEPA/CEQA Process
One joint NEPA/CEQA document will be prepared
NEPA: National Environmental Policy Act
CEQA: California Environmental Quality Act
NEPA/CEQA review will require studies of impacts including:
Cultural resources, Air Quality, Biological resources, Traffic
Warehouse #1 may be eligible to be listed as a historic resource under CEQA
Demolition of Warehouse #1 could potentially effect the level of environmental documentation
Potential Project Construction Permits identified and listed in Report
Potential Terminal Operating Permits identified and listed in Report
12. Cost Estimates Environmental Document Preparation:
Historic Evaluation of Warehouse #1: $10,000 to $12,000
EA/ND: $85,000
EIS/EIR: $190,000
Wharf Redevelopment Plan:
Wharf with complete demolition: $15,329,000
Wharf with partial demolition: $12,782,000
Costs shown include:
Demolition and removal of existing timber structures
Pile supported concrete platform with two approach trestles
Fender elements, bollards and other hardware
Line handler walkways between existing breasting dolphins
Electrical power distribution system upgrades
Contractor mob/demob, project administration, overhead & profit
Expenses for bonds, engineering, testing, inspection, construction management
15% allowance for contingency
13. Cost Estimates Site Redevelopment Plan:
Landside infrastructure improvements: $996,000
Cost includes:
Demolition and removal Warehouse #1 and foundations
Removal of existing rail adjacent to Wharves 1 and 2
Improved access road adjacent to waterfront
Rail crossing and intersection improvements at Hinman Road
Longshoremen/Stevedore’s building with paved parking area
Service improvements including electrical, communications, potable water, sewer and drainage
Contractor overhead & profit
Expenses for bonds, engineering, testing, inspection, construction management
15% allowance for contingency
Cost excludes:
Purchase and installation of new hopper and conveyor system
Realignment of HS&G/CEMEX storage yard; relocation of existing equipment
Soil improvements, if required to accommodate new stockpile location
14. Project Schedule DESIGN-BID-BUILD vs. DESIGN-BUILD:
The Port may opt to follow either contracting method
Design-Bid-Build:
Port advertises for and selects an A/E Firm to design the project
Second advertisement and selection for a contractor to build the project using A/E Firm’s plans and specifications
Traditional contracting method
A/E Firm works for Port and Port has more input into details of design
Design-Build:
Port advertises for and selects an A/E-Contractor team to design and construct the project
Generally results in an overall reduction in project cost and shorter schedule to delivery
Disputes between A/E Firm and Contractor eliminated
Has recently become the contracting method of choice for many owners
RECOMMENDATION:
Overall cost difference between contracting methods not substantial
If project timeline is critical factor, recommend Design-Build contract
15. Project Schedule OVERALL PROJECT SCHEDULE:
Time-line from the start of Environmental Documents to completion:
Design-Bid-Build contract: 30 to 33 months (EA/ND or EIS/EIR)
Design-Build contract: 24 to 27 months
ENVIRONMENTAL DOCUMENTS and PERMITTING:
Historic Evaluation of Warehouse #1: 2 months
Following Historic Evaluation, level of Environmental Documentation determined
EA/ND: 6 months
EIS/EIR: 9 months
Permitting follows Environmental Document: 5.5 months
16. Project Schedule
17. Project Execution Plan WHERE DO WE GO FROM HERE?
Work with HS&G/CEMEX to install temporary system to relocate ship unloading operations closer to Wharf 2 and away from RMC/CEMEX cement wharf.
Perform Economic Evaluation/Impact Analysis of wharf replacement
Phased construction planning is possible
Initiate Warehouse #1 Historic Review
Results of assessment will determine the level of NEPA/CEQA review
Prepare Environmental Document(s)
Prepare RFP documents to advertise and select a Design/Design-Build Contractor to initiate project design and construction
19. Phase 1 ACTIVITIES:
Reviewed and evaluated cargo data provided by the Port
Provided cargo projections based on data
Completed a ‘Mini-Master Plan’ of the complete Port facility with primary focus on the best use for the redevelopment of Wharves 1 and 2
CONCLUSIONS:
Fundamental need for improving Wharves stems from poor current physical condition
Wharves 1 and 2 are critical to the Port revenue stream and must be maintained
BCDC lists Redwood City as a critical element in the BCDC Plan for bulk cargoes
Primary cargoes at Wharves 1 and 2 is now and is forecasted to be dry bulk
Cargo handling flexibility is a key consideration, but must be able to efficiently handle dry bulk cargoes
20. Phase 2 ACTIVITIES:
Assessed terminal requirements
Developed various wharf and site redevelopment plans
Completed Structural and Geotechnical review of design options
Developed conceptual-level cost estimates for design alternatives
Completed an Environmental and Permitting review of design options
Recommended a final Marine Terminal Plan
CONCLUSIONS:
Construct a nominally 60’ wide by 490’ long platform with two approach trestles in the location of Wharf 2 and the southwest end of Wharf 1.
Concrete pile supported concrete platform, 500psf design deck load
Relocate the ship unloading hopper to enable the ship unloading operation to move closer to Wharf 2 and away from the CEMEX cement vessels
Raze Warehouse #1 and realign HS&G/CEMEX lease area to provide the Port with additional land for future development opportunities
21. Phase 3 ACTIVITIES:
Further developed plans and cost estimates for Preferred Marine Terminal Plan
Completed Environmental and Permitting review and assessment
Developed Project Execution Plan and Schedules
CONCLUSIONS:
Demolition plan and recommendations
Environmental and Permitting assessment
Wharf design concepts finalized
Interim Conveyor Plan – relocate ship receiving hopper away from cement berth
Cost Estimates:
Environmental Document preparation
Wharf construction with partial or complete demolition of existing wharf
Landside infrastructure construction
Project Schedules
NEXT STEPS:
“Where do we go from here?”