E nviromental I mpact S tatement. D evelopment P roposals for the B arkarby F ield. S. B engoa X avier N aldi C hiara S ai F lorence K ai K warteng O wusu A kyaw I llueca M unoz J acobo & S tojanovski T odor. P r e s e n t. O ctober 13 th. P resentation. EIS.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' E nviromental I mpact S tatement' - adah


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

EnviromentalImpactStatement

Development Proposals for the Barkarby Field

S

Bengoa Xavier

Naldi Chiara

Sai Florence Kai

Kwarteng Owusu Akyaw

Illueca Munoz Jacobo &

Stojanovski Todor

P r e s e n t

October 13th

Presentation

slide2
EIS

Description of Alternatives

slide5

Zero-Alternative

  • The proposed development does not take place
  • The Barkarby Airport remains
  • No -or few- new housing in the area
slide6

Zero-Alternative

  • Increasing road traffic of approx. 2% per year
  • Increasing noise pollution (plane and road traffic)
  • Increasing air pollution (plane and road traffic)
slide7

Zero-Alternative

  • Expansion of the IKEA commercial area in the south
  • Creation of a Natural Reserve around the Igelbäcken
  • Slow restoration of military damaged forests
slide8

Alternative 2

The ”Anatomic” development

slide10

Alternative 2

  • The ”Anatomic” development
  • The smallest option
  • All around the Barkarby village with a green belt in between
slide11

Alternative 2

  • Area concerned: 86.5 hectares
  • 4600 new inhabitants
  • 11 housing areas (9 with apartments – 2 with villas)
  • No public transport network
slide12

Description of Alternatives

Alternative 4

The ”American Dream” development

slide14

Alternative 4

  • The ”American Dream” development
  • The medium-sized option
  • Mixed use: housing & commercial/business
  • Only on the North of Norrviksvägen
slide15

Alternative 4

  • Area concerned: 95.49 hectares
  • 7170 new inhabitants & 3640 work places
  • 6 housing areas (6 with apartments – 2 with villas) & 3 commercial/business areas
  • Bus network, pedestrian and cycling paths in the housing areas
slide16

Alternative 12

Description of Alternatives

The ”Tutti Frutti” development

slide18

Alternative 12

  • The ”Tutti Frutti” development
  • The biggest option
  • Mixed use: housing & commercial/business
  • Around the village of Barkarby

(North, East and South)

slide19

Alternative 12

  • Area concerned: 133 hectares
  • 11000 new inhabitants
  • 7 housing areas, all with apartments & some commercial areas (undefined)
  • New tunnel under the whole area moving the transiting traffic
  • Bus network, pedestrian and cycling paths
slide20
EIS

Traffic

Air Quality

traffic assumptions
Traffic Assumptions
  • Traffic increase 2% per year
  • Timescale of 10 years
slide22

Air Quality

CO Emissions

slide28

Air Quality

NO2 Emissions

main facts
Main Facts
  • NO2 is the only pollutant to be considered
  • Not a major threat over 10 meters
  • Motorway represents the main pollutant source
slide35
EIS

Traffic

Noise Impact

mitigation measures
Mitigation Measures
  • Public-bus network
  • Speed limit
  • No-building area
  • Screens
slide45
EIS

Hydrology

Water Quality & Runoff

runoff
Runoff
  • Baseline runoffs:
  • Igelbäcken 45 l/s
  • Bällstaån 120 l/s
runoff1
Runoff
  • Very small runoff increase
  • Cumulative impacts. Be careful!!!
water quality
Water Quality
  • Less nitrogen released
  • Phosphorus increase in Bällstaån
main facts1
Main Facts
  • Overflow will increase
  • Improved water quality
slide50
EIS

Ecology

Flora, fauna & landscape

slide51

Impacts on Landscape

  • 0 Alternative  Fragmentation
  • Other alternatives  Opens the ”Green wedge”
slide52

Impacts on Flora

Deciduous, coniferous, oak trees, grass

  • Only impact will be on the edge of the forests (ecotones) for alternative 2 and 4
slide53

Impacts on Fauna

Stone Loach and Spinned Loach

  • Alternative 4 and 12 are close to the Igelbäcken  Impact on fish
  • Mitigation  Restricted access to the stream
population economic growth
Population & Economic Growth
  • Population base & high level for the municipality (Regional plan)
  • Green buildings concept
green buildings concept
Green buildings concept
  • "Typical" buildings consume more of our resources than necessary, negatively impact the environment, and generate a large amount of waste.
  • Energy efficiency, use renewable energy
  • Water conservation
  • Waste minimization
  • Reduced operation and maintenance costs
slide61

Public Participation

  • Interviews & questionnaires
  • Meetings
slide62
EIS

Monitoring

slide64
EIS

Conclusion &

Recommendations

slide65

No big difference between the alternatives for environmental impacts

  • Big differences in social impacts

 We decide to recommend

Alternative 4

slide66

Better balance between the needs for housing and the economic development of the area

  • Avoids uncertainty concerning further development of the IKEA commercial area
slide67

Very good public transport network

  • Limited impact on the environment (no excavation, no deforestation)
  • Improvement of water quality (especially in the Igelbäcken)