1 / 15

Utility Subordinations

Utility Subordinations. “An Overview”. PRESENTED BY:. Jim Lormann – EMBARQ Real Estate Manager III Real Estate Transactions & Anaylsis Trisha Miller – D5 FDOT D5 Utilities Project/Value Manager. WHAT IS IT?. Subordination of Utility Easement interest, from the Utility Owner to the FDOT.

ada
Download Presentation

Utility Subordinations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utility Subordinations “An Overview”

  2. PRESENTED BY: • Jim Lormann – EMBARQ Real Estate Manager III Real Estate Transactions & Anaylsis • Trisha Miller – D5 FDOT D5 Utilities Project/Value Manager

  3. WHAT IS IT? • Subordination of Utility Easement interest, from the Utility Owner to the FDOT. • This occurs when FDOT buys part, or all of a private parcel, which has a Utility Easement within it.

  4. THE DOCUMENT

  5. THE DOCUMENT (cont.)

  6. THE DOCUMENT (cont.)

  7. THE DOCUMENT (cont.)

  8. THE ATTACHMENTS • The Recorded Utility Easement • The Sketch of the Parcel

  9. WHAT‘s IN IT FOR ME? • If a Utility Owner has property rights through an easement on a private parcel, FDOT WILL PAY for any relocation required. • This applies to the CURRENT project underway, and any FUTURE project which may create additional relocation.

  10. THE PROCESS, FDOT • The Department will send to the UAO with all the attachments • Then UAO executes and sends back to the Department • The Department sends it to the Clerks Office for recording • Once recorded the Department will forward back to the UAO

  11. THE PROCESS, UAO • The UAO receives document • The UAO reviews document • The UAO routes to internally impacted groups (i.e. engineering) for review and comments. • The UAO contacts FDOT to discuss any outstanding issues with FDOT. • The UAO negotiates with FDOT on reimbursement amount and any other terms or conditions.

  12. THE PROCESS,UAO (cont.) • The UAO routes the Document to Legal for review and approval. • The UAO routes document for approval and execution. • The UAO returns approved documents including cost estimates to FDOT • The UAO sets up relocation project for tracking.

  13. WHAT’s THE RUSH? • FDOT Right of Way needs to have parcels executed and closed before they can certify the right of way as “clear”. • To accomplish this, they must address all easement interests within the parcel.

  14. Lessons Learned • FDOT must assure that all Utility Subordination packages are complete when they go out to the Utility Owners. • The UAO’s need to get them through their engineering and legal departments to expedite a timely response. • The Subordination must be executed by a Vice President or President of a private Utility Owner. If it is a City/County owned utility, it must go to Commission/Council for approval and execution.

  15. QUESTIONS ?