1 / 20

NCDOT Project Delivery Improvement Recommendations

NCDOT Project Delivery Improvement Recommendations. Prepared for: North Carolina General Assembly July 3, 2007. Introduction. Tom Barry Senior Vice President PBS&J Southeast Regional Transportation Manager Former Florida DOT Secretary Held a wide variety of FDOT positions including:

PamelaLan
Download Presentation

NCDOT Project Delivery Improvement Recommendations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NCDOT Project Delivery Improvement Recommendations Prepared for:North Carolina General AssemblyJuly 3, 2007

  2. Introduction • Tom Barry • Senior Vice President PBS&J Southeast Regional Transportation Manager • Former Florida DOT Secretary • Held a wide variety of FDOT positions including: • Assistant Secretary for Finance and Administration • Secretary and Director of Production: District Five • Professional Engineer -2-

  3. Introduction • Gene Conti • Vice President PBS&J Mid South District Director • Former Chief Deputy Secretary North Carolina DOT • Held transportation related positions: • Assistant Secretary Transportation Policy USDOT • Deputy Assistant Secretary for Budget and Programs USDOT • Secretary Maryland Department of Labor, Licensing, and Regulation -3-

  4. NCDOT Project DeliveryImprovement Recommendations • 12-week study focusing on NCDOT’s TIP delivery processes through three tasks: • Reviewed TIP management and overall project delivery process • Reviewed NCDOT and resource agency approaches to environmental reviews and permitting • Performed Value Engineering studies for specific TIP projects -4-

  5. TIP Management andOverall Project Delivery Process • Review focused on major project-delivery issues raised in the Dye Management report • Predictability, accountability, communications for project delivery • Overall project-delivery process (specifically development/delivery TIP and use of alternative-delivery options) • Causes of delay • Project-management principles/practice -5-

  6. TIP Management andOverall Project Delivery Process • Conducted interviews with: • Senior NCDOT staff • Former NCDOT staff • Transportation industry leaders and organizations -6-

  7. TIP Management andOverall Project Delivery Process • Findings • Predictability, accountability, communications for project delivery: • Minimal progress on Dye Management recommendations • 12-month/36-month lists • Delivery/Development TIP -7-

  8. TIP Management andOverall Project Delivery Process • Findings • Overall project-delivery process: • Delivery TIP – Value Engineering efforts • Alternative Delivery • “Turn-key” consultant contracts • Intrastate design alternatives -8-

  9. TIP Management andOverall Project Delivery Process • Findings • Causes of delay – environmental process: • Lead agency/elevation • Causes of delay – consultant procurement/management: • Threshold raised to $250,000 • PDEA coordinated contracting approach • Procurement alternatives -9-

  10. TIP Management andOverall Project Delivery Process • Findings • Project-management principles/practice: • Very little progress – PM positions almost non-existent, no Program Delivery oversight • PMii offers potential for major gains • Leadership seems receptive to change – McKinsey effort -10-

  11. TIP Management andOverall Project Delivery Process • Recommendations • Begin immediately to establish “Project Management” as the overall guiding philosophy for NCDOT. • Begin to use PMii both as a project-management tool and as a broader reporting mechanism. This can be achieved easily within the next 6 months. • Begin the new TIP cycle this summer, with the goal of having a measurable and realistic first- year work plan developed by May 2008, to be implemented for the second year of the TIP. • Develop and test alternative pre-construction scoping and contracting mechanisms to determine if significant time- or cost savings can be achieved through these new approaches. • Identify 10 pilot projects to test the “team delivery” concepts, using PM principles and methodologies. -11-

  12. Environmental Reviews and Permitting • Study Overview • Reviewed environmental policies including: • NEPA/404 Merger 01 process • NC Ecosystem Enhancement Program (EEP) • Stream Mitigation Guidelines • SAFETEA-LU and Environmental Streamlining • Conducted interviews with: • FHWA • NCDOT • USACE • NCDWQ • EPA • Consultants -12-

  13. Environmental Reviews and Permitting • Findings • Merger/SAFETEA-LU Section 6002 • Merger process is longer for planning purposes, may save permitting time • Section 6002 more clearly places DOT in lead role • Merger process generally produces more detailed study alternatives and higher levels of design • Section 6002 would allow more Categorical Exclusions than current Merger process/guidelines -13-

  14. Environmental Reviews and Permitting • Findings • NC Ecosystem Enhancement (EEP) • Has reduced “mitigation” risk • Initial costs were high; recent changes • Stream Buffer Guidelines • Encouraged longer, more costly bridging in certain river basins (Tar, Neuse) • Resource Agency Funding • Significant investments have been made (over 30 positions now funded) -14-

  15. Environmental Reviews and Permitting • Merger 01/Section 6002 Recommendations • NCDOT should reaffirm lead-agency status • NCDOT should use the “elevation” process more frequently • Consider endangered species prior to CP 2a • Expand the Categorical Exclusion process to include road widening projects • Execute level of design appropriate to exclude alternatives -15-

  16. Environmental Reviews and Permitting • Other Recommendations • Eliminate NCDOT’s Bridge Buffer memorandum • Improve NCDOT’s GIS database • Provide Merger 01 training periodically and for new staff • Provide up-to-date computer equipment and software when needed -16-

  17. TIP ProjectsValue Engineering • Study Overview • Ten various TIP projects selected for study • Each project costs over $25 million • Each project programmed for final design/project letting within 2 to 4 years -17-

  18. TIP ProjectsValue Engineering • Study Results -18-

  19. TIP ProjectsValue Engineering • Recommendations • Cost awareness • Construction cost knowledge • Right-of-Way • Median width and type • Context-sensitive design -19-

  20. TIP ProjectsValue Engineering Thank You!

More Related