Auburndale High School Masterplan. Construction Progress Update 5/17/10. A.H.S.- Phase I Project Highlights. Sitework / Demolition Demolition of Buildings 1, 2, 3, 7, 10 and 88 New Water, Storm, Sewer & Fire Lines for campus Decorative Aluminum Security Fencing between buildings

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Auburndale High School Masterplan' - Olivia


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
auburndale high school masterplan

Auburndale High School Masterplan

Construction Progress Update

5/17/10

a h s phase i project highlights

A.H.S.- Phase I Project Highlights

Sitework / Demolition

Demolition of Buildings 1, 2, 3, 7, 10 and 88

New Water, Storm, Sewer & Fire Lines for campus

Decorative Aluminum Security Fencing between buildings

New walkway canopies & sidewalks through-out campus

New Parent Drop off Loop & Parking Areas

Portion of project is 35% Complete

Large portion of water & fire lines are completed

Demo of Buildings 1, 2, 3, 10, and 88 completed

Stormwater Ponds are mostly completed

Will be complete for Fall 2010 Semester

a h s phase i project highlights12

A.H.S.- Phase I Project Highlights

Addition to Auditorium- 13,271SF

New Band, Chorus, Piano Lab, and Orchestra Rooms

Offices and Storage Rooms

Practice Rooms

Renovations to Auditorium

Fire Sprinkle Building

New Loading Dock and Backstage Storage Areas

Portion of project is 35% Complete

Slab and Block walls completed

Steel joist to begin this week

Will be completed for Fall 2010 Semester

a h s phase i project highlights17

A.H.S.- Phase I Project Highlights

Major Renovations to North Campus Building

Create New Media Center

New Pre-K Classrooms and Playground

New efficient HVAC, Fire Alarm, Intercom, and Data systems in existing classrooms

Added windows on the north and south of Building

New Career Center, Computer Labs and Conference Room

Portion of project is 40% Complete

Demo, rough-ins and drywall complete in Media Center

Demo for Pre-K areas to begin this week

1st set of 5 classrooms with new HVAC complete

Will be completed for Fall 2010 Semester

a h s phase i project highlights22

A.H.S.- Phase I Project Highlights

New EHPA Cafeteria Building

17,315SF building

Will serve as a Hurricane Shelter for the Community

Full new kitchen

Covered Outdoor seating area

Portion of project is 8% Complete

2/3 of stem walls are completed

2/3 of slab will be poured this week

Will be completed in early 2011

a h s phase i project highlights26

A.H.S.- Phase I Project Highlights

New Football Concession Stand Building

Separate 704SF Structure on southern side of grandstands

Stainless Steel Countertops

Storage Areas

Includes concrete patio area

Portion of project is 80% Complete

Walls and Trusses installed, roof is dried-in

Sanitary Sewer work completed

Will be complete Summer of 2010

a h s phase i project highlights30

A.H.S.- Phase I Project Highlights

Renovations to Gymnasium

New Lobby area with Trophy Cases and large windows

New, impact resistant windows for Gym

Screen walls to conceal HVAC units on Lobby roof

New Exterior Sign:

“Home of the Bloodhounds”

Portion of project is starting this week

All sports and events are completed so work can begin

Locker rooms will remain in use during construction

Will be complete for Fall 2010 Semester

a h s phase ii project highlights

A.H.S.- Phase II Project Highlights

Demolition of old Cafeteria Building

New Classroom Building

19,411 SF, 1-Story, 13 Classroom Building

Teacher’s Offices

Storage Rooms

Includes walkway canopies for south side of campus

Remodeled Building #22

5,000SF Building

Complete interior demolition and renovations

Will serve as new JROTC facility

Portion of project will start in early 2011 once new Cafeteria and old Cafeteria is demolished

a h s phase iii project highlights

A.H.S.- Phase III Project Highlights

New Freshman Academy Building

52,800SF, 2-Story, 27 Classroom Building

Administrative Spaces

ESE Teaching Spaces

Science Labs and Demo Rooms

Media Center

Teacher’s Offices and Storage Rooms

Softball Complex

Relocated, New Field

New Concession Stand building with restrooms

Portion of project is approved by the Board, and currently awaiting funding

auburndale high school masterplan36

Auburndale High School Masterplan

Construction Progress Update

5/17/10