Auburndale High School Masterplan

Auburndale High School Masterplan. Construction Progress Update 5/17/10. A.H.S.- Phase I Project Highlights. Sitework / Demolition Demolition of Buildings 1, 2, 3, 7, 10 and 88 New Water, Storm, Sewer & Fire Lines for campus Decorative Aluminum Security Fencing between buildings

Olivia
Download Presentation

Auburndale High School Masterplan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Auburndale High School Masterplan Construction Progress Update 5/17/10

  2. A.H.S.- Phase I Project Highlights Sitework / Demolition Demolition of Buildings 1, 2, 3, 7, 10 and 88 New Water, Storm, Sewer & Fire Lines for campus Decorative Aluminum Security Fencing between buildings New walkway canopies & sidewalks through-out campus New Parent Drop off Loop & Parking Areas Portion of project is 35% Complete Large portion of water & fire lines are completed Demo of Buildings 1, 2, 3, 10, and 88 completed Stormwater Ponds are mostly completed Will be complete for Fall 2010 Semester

  3. Site Photos- Before

  4. Building #1- Being Demolished

  5. Building #1- Being Demolished

  6. Building #1 Demolished

  7. A.H.S.- Phase I Project Highlights Addition to Auditorium- 13,271SF New Band, Chorus, Piano Lab, and Orchestra Rooms Offices and Storage Rooms Practice Rooms Renovations to Auditorium Fire Sprinkle Building New Loading Dock and Backstage Storage Areas Portion of project is 35% Complete Slab and Block walls completed Steel joist to begin this week Will be completed for Fall 2010 Semester

  8. Auditorium Addition- Before

  9. Auditorium Addition

  10. Auditorium Addition

  11. Auditorium Addition

  12. A.H.S.- Phase I Project Highlights Major Renovations to North Campus Building Create New Media Center New Pre-K Classrooms and Playground New efficient HVAC, Fire Alarm, Intercom, and Data systems in existing classrooms Added windows on the north and south of Building New Career Center, Computer Labs and Conference Room Portion of project is 40% Complete Demo, rough-ins and drywall complete in Media Center Demo for Pre-K areas to begin this week 1st set of 5 classrooms with new HVAC complete Will be completed for Fall 2010 Semester

  13. North Campus Building- Before

  14. New Media Center

  15. New Career Center

  16. N. Campus Classroom Renovations

  17. A.H.S.- Phase I Project Highlights New EHPA Cafeteria Building 17,315SF building Will serve as a Hurricane Shelter for the Community Full new kitchen Covered Outdoor seating area Portion of project is 8% Complete 2/3 of stem walls are completed 2/3 of slab will be poured this week Will be completed in early 2011

  18. Cafeteria Location- Before

  19. New EHPA Cafeteria

  20. New EHPA Cafeteria

  21. A.H.S.- Phase I Project Highlights New Football Concession Stand Building Separate 704SF Structure on southern side of grandstands Stainless Steel Countertops Storage Areas Includes concrete patio area Portion of project is 80% Complete Walls and Trusses installed, roof is dried-in Sanitary Sewer work completed Will be complete Summer of 2010

  22. New Football Concession Stand

  23. New Football Concession Stand

  24. New Football Concession Stand

  25. A.H.S.- Phase I Project Highlights Renovations to Gymnasium New Lobby area with Trophy Cases and large windows New, impact resistant windows for Gym Screen walls to conceal HVAC units on Lobby roof New Exterior Sign: “Home of the Bloodhounds” Portion of project is starting this week All sports and events are completed so work can begin Locker rooms will remain in use during construction Will be complete for Fall 2010 Semester

  26. Existing Gym Signage & HVAC Units

  27. Existing Gymnasium Windows

  28. A.H.S.- Phase II Project Highlights Demolition of old Cafeteria Building New Classroom Building 19,411 SF, 1-Story, 13 Classroom Building Teacher’s Offices Storage Rooms Includes walkway canopies for south side of campus Remodeled Building #22 5,000SF Building Complete interior demolition and renovations Will serve as new JROTC facility Portion of project will start in early 2011 once new Cafeteria and old Cafeteria is demolished

  29. Existing Building #22

  30. A.H.S.- Phase III Project Highlights New Freshman Academy Building 52,800SF, 2-Story, 27 Classroom Building Administrative Spaces ESE Teaching Spaces Science Labs and Demo Rooms Media Center Teacher’s Offices and Storage Rooms Softball Complex Relocated, New Field New Concession Stand building with restrooms Portion of project is approved by the Board, and currently awaiting funding

  31. Auburndale High School Masterplan Construction Progress Update 5/17/10