An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome to the Jurisdiction of Unit-1 R.S.R.D.C. Ltd., Ajmer

  2. ORGANISATION CHART OF RSRDC UNIT-1, AJMER RE Rakesh Kr. Jain AAO Sh. Shiv Kr. Sharma ARE Sh. Brijesh Kr. Mathur ARE. Sh. Avinash Kumar ARE Sh. N.K. Tak ARE Sh. J.P. Kansal ARE Sh. Harsh Rai J.En. (Elect.) Sh. O.P. Sharma

  3. Financial Work Load in Unit Rs. in Lacs.

  4. Rs. in Lacs. Financial Work Load in Unit

  5. Financial Work Load in UnitRs. in Lacs.

  6. Financial Work Load in UnitRs. in Lacs.

  7. Financial Work Load in UnitRs. in Lacs.

  8. Important Works Completed during last 5 years Bharat Vidhya Adhayan Sankul at M.D.S.U., Ajmer Completion Cost – Rs. 1.10 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education Rajasthan State Sh. Ghanshyam Tiwari in March, 07 Inaugurated by Prof. Sukhdev Thorat Chairman UGC on 12.10.09

  9. Important Works Completed during last 5 years Boy’s Hostel at M.D.S.U., Ajmer Completion Cost – Rs. 1.65 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education Rajasthan State Sh. Ghanshyam Tiwari in March, 07

  10. Important Works Completed during last 5 years Girls Hostel at M.D.S.U., Ajmer Completion Cost – Rs. 1.40 Crs. Completion Cost – Rs. 1.65 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education & PWD Rajasthan State Sh. Lalit Kishor Chaturvedi on 24.09.1998 Inaugurated by Honble Mininster for Higher Education Rajasthan State Govt. Sh. Ghanshyam Tiwari on 21.08.2006

  11. Important Works Completed during last 5 years Social Science Block at M.D.S.U., Ajmer Completion Cost – Rs. 3.05 Crs. Foundation Stone laid by Hon’ble Minister for Mahilla Bal Vikas & JanJati Kashetrya Vikas, Rajasthan State Sh. Kankmal Kataraon 01.06.2005. Inaugurated by Honble Mininster for Higher Education Rajasthan State Govt. Sh. Ghanshyam Tiwari on 10.08.2006.

  12. Important Works Completed during last 5 years Yoga Centre at M.D.S.U., Ajmer Completion Cost – Rs. 0.63 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education & PWD Rajasthan State Sh. Lalit Kishor Chaturvedion 24.09.1998 Inaugurated by Honble Mininster for Higher Education Rajasthan State Govt. Sh. Ghanshyam Tiwari on 29.06.2007.

  13. Important Works Completed during last 5 years Women Engineering College at Ajmer Completion Cost – Rs. 2.57 Crs. Foundation Stone laid by Hon’ble Chief Minister Govt. of Rajasthan Smt. Vasundhra Raje on 30.04.07 Handed Over in November, 2009

  14. Important Works Completed during last 5 years Women Engineering College at Ajmer Completion Cost – Rs. 2.57 Crs. Foundation Stone laid by Hon’ble Chief Minister Govt. of Rajasthan Smt. Vasundhra Raje on 30.04.07 Handed Over in November, 2009

  15. Important Works Completed during last 5 years Management Block at M.D.S.U., Ajmer Completion Cost – Rs. 1.97 Crs. Inaugurated by Honble Mininster for Industries Rajasthan State Govt. Sh. Rajendra Pareek on 17.09.09.

  16. Important Works Completed during last 5 years New Answer Book Halls at 1st Floor & 2nd Floor in B.S.E.R., Ajmer Completion Cost – Rs. 2.15 Crs. Handed Over in November, 2009

  17. Important Works Completed during last 5 years Engineering College, Ajmer Completion Cost – Rs. 5.40 Crs. Inaugurated by Honble Chief Mininster Govt. of Rajasthan Smt.Vasundhra Raje on 25.01.08.

  18. POLICE HOUSING SCHEME (ONGOING WORK AT GRP CAMPUS) No. of Quarters : 304 Nos. (L.S.Q.-292 + U.S.Q.-12) Total Cost : 15.73 Crores Location : G.R.P. Campus, Nareli, Ajmer Date of Start : February, 2008 / October, 2008 Stipulated Date of Completion : January, 2009 / September, 2009 Expenditure till Date : 12.09 Crores Likely Completion date : March, 2010 Bottlenecks if any : (i) Sanction for Development works not given. (ii) Water supply connection in campus is to be carried out by PHED. For which Six Months period required. (iii) 60 Nos Qtrs. (L.S.Q.) taken in Phase-II

  19. POLICE HOUSING SCHEME (ONGOING WORK AT GRP CAMPUS)

  20. POLICE HOUSING SCHEME (ONGOING WORK AT RAC,NARELI CAMPUS) No. of Quarters : 108 Nos. (L.S.Q.-104 + U.S.Q.-4) Total Cost : 5.55 Crores Location : R.A.C. Campus, Nareli, Ajmer Date of Start : February, 2008 / October, 2008 Stipulated Date of Completion : January, 2009 / September, 2009 Expenditure till Date : 3.78 Crores Likely Completion date : March, 2010 Bottlenecks if any : (i) 56 L.S.Q. taken in Phase-II work in month of October, 2008 therefore, campus may be ready for handing over by March, 2010.

  21. Name of Work:- Various Works in M.D.S. University, Ajmer Construction of First Floor at Computer Centre • Total Cost : 0.54/0.79 Crore • Location : M.D.S. University, Campus • Date of Start : September, 2008 • Stipulated Date of Completion : April, 2009 • Expenditure till Date : 0.53 Crore • Likely Completion date : March, 2010 • Bottlenecks if any : Revised Sanction for additional work received in June, 2009 and delay in payment from client.

  22. Name of Work:- Various Works in M.D.S. University, Ajmer Construction of Women Hostel Foundation Stone Lead by Hon’ble State Minister for Information Technology & Communication Govt. of India Sh. Sachin Piolet on 15th September, 2009 • Total Cost : 1.81 Crores • Location : M.D.S. University, Campus • Date of Start : September, 2009 • Stipulated Date of Completion : June, 2010 • Expenditure till Date : 0.08 Crore • Likely Completion date : June, 2010 • Bottlenecks if any : Work started in October, 2009 due to foundation stone ceremony in September, 2009.

  23. Name of Work:- Various Works in M.D.S. University, Ajmer Construction of Academic Staff College (Guest House) • Total Cost : 0.75 Crore • Location : M.D.S. University, Campus • Date of Start : August, 2009 • Stipulated Date of Completion : December, 2009 • Expenditure till Date : 0.11 Crore • Likely Completion date : March, 2010 • Bottlenecks if any : Funds not released by client timely.

  24. Name of Work:- Various Works in M.D.S. University, Ajmer Construction of Environmental Science Building Foundation Stone Lead by Hon’ble State Minister for Information Technology & Communication Govt. of India Sh. Sachin Piolet on 15th September, 2009 • Total Cost : 2.39 Crores • Location : M.D.S. University, Campus • Date of Start : December, 2009 • Stipulated Date of Completion : November, 2010 • Expenditure till Date : 0.00 Crore • Likely Completion date : November, 2010 • Bottlenecks if any : -

  25. Name of Work:- Various Works in Board of Sec. Edu., Rajasthan, Ajmer Construction of Parking, Office, Chamber & Auditorium • Total Cost : 14.00 Crores • Location : B.S.E.R. Campus • Date of Start : September, 2008 • Stipulated Date of Completion : August, 2011 • Expenditure till Date : 2.89 Crores • Likely Completion date : August, 2011 • Bottlenecks if any : Work stopped on account of decision not given by client for Construction of Auditorium hence, Construction of 2rd Floor held up for Two Months.

  26. Name of Work:- Various Works in Board of Sec. Edu., Rajasthan, Ajmer Construction of 1st & 2nd Floor on Old Answer Book Hall • Total Cost : 1.06 Crores • Location : B.S.E.R. Campus • Date of Start : September, 2008 • Stipulated Date of Completion : February, 2010 • Expenditure till Date : 0.49 Crore • Likely Completion date : March, 2010 • Bottlenecks if any : (i) Funds not released by client timely. • (ii)Work stopped by client on account of thorough passes for access of examination stationary through trucks.

  27. Name of Work:- Various Works under Police Modernization Construction of Adm. Training Block at PTS Kishangarh • Total Cost : 1.5 Crores • Location : Kishangarh • Date of Start : September, 2008 • Stipulated Date of Completion : May, 2009 • Expenditure till Date : 1.30 Crores • Likely Completion date : January, 2010 • Bottlenecks if any : Part sanction of Rs. 0.5 crores received in phase-II.

  28. Name of Work:- Various Works under Police Modernization Construction of Hostel Building of Trainee at PTS Kishangarh Total Cost : 1.00 Crore Location : Kishangarh Date of Start : September, 2008 Stipulated Date of Completion : May, 2009 Expenditure till Date : 0.55 Crore Likely Completion date : January, 2010 Bottlenecks if any : Part sanction of Rs. 0.2 crores received in phase-II.

  29. Name of Work:- Various Works under Police Modernization Construction of Adm. Building for RPL, Hadi Rani Battalion, Ajmer • Total Cost : 1.25 Crores • Location : Nareli, Ajmer • Date of Start : January, 2009 • Stipulated Date of Completion : December, 2009 • Expenditure till Date : 0.31 Crore • Likely Completion date : January, 2010 • Bottlenecks if any : Work Started in July, 2009 due to non availability of land.

  30. Name of Work:- Various Works under Police Modernization Construction of 100 mens barracks at RPL, Hadi Rani Battalion, Ajmer (Part-I) • Total Cost : 1.00 Crore • Location : Nareli, Ajmer • Date of Start : January, 2009 • Stipulated Date of Completion : December, 2009 • Expenditure till Date : 0.03 Crore • Likely Completion date : January, 2010 • Bottlenecks if any : Work Started in July, 2009 due to non availability of land.

  31. Name of Work:- Various Works under Police Modernization Construction of 100 mens barracks at RPL, Hadi Rani Battalion, Ajmer (Part-II) • Total Cost : 1.00 Crore • Location : Nareli, Ajmer • Date of Start : January, 2009 • Stipulated Date of Completion : December, 2009 • Expenditure till Date : 0.006 Crore • Likely Completion date : January, 2010 • Bottlenecks if any : Work Started in July, 2009 due to non availability of land.

  32. Name of Work:- Various other works in Unit-I, Ajmer Construction of Canteen cum Guest House at Engineering College, Ajmer • Total Cost : 0.42 Crore • Location : Ajmer • Date of Start : December, 2007 • Stipulated Date of Completion : July, 2008 • Expenditure till Date : 0.26 Crore • Likely Completion date : March, 2010 • Bottlenecks if any : -

  33. Name of Work:- Various other works in Unit-I, Ajmer Construction of Urban Hatt at Ajmer • Total Cost : 1.60 / 1.90 Crores • Location : Ajmer • Date of Start : June, 2007 • Stipulated Date of Completion : May, 2008 • Expenditure till Date : 1.14 Crores • Likely Completion date : March, 2010 • Bottlenecks if any : Work Stopped since October, 2008 due to funds not released by client

  34. Proposed New Works