Sarasota memorial health care system management council february 10 2010
Download
1 / 10

Sarasota Memorial Health Care System Management Council February 10, 2010 - PowerPoint PPT Presentation


  • 218 Views
  • Uploaded on

Sarasota Memorial Health Care System Management Council February 10, 2010. Construction Milestone Schedule. Project Milestones – Surgery Vertical Expansion:. Preparation for Structural Steel Close Arlington Street Capture Site Set up Crane for Structural Steel Open Arlington Street.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Sarasota Memorial Health Care System Management Council February 10, 2010' - EllenMixel


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Sarasota memorial health care system management council february 10 2010 l.jpg

Sarasota Memorial HealthCare SystemManagement Council February 10, 2010



Project milestones surgery vertical expansion l.jpg

Project Milestones – Surgery Vertical Expansion:

  • Preparation for Structural Steel

  • Close Arlington Street

    Capture Site

    Set up Crane for Structural Steel

  • Open Arlington Street

Target Start – 2/22/10

Target Start – 4/12/10

Target Start - 12/31/10


Site phasing diagram surgery vertical expansion l.jpg

Site Phasing Diagram – Surgery Vertical Expansion

Ambulance Access to be Maintained at All Times

Construction Zone for Crane, Material Deliveries, etc.


Project milestones new bed tower l.jpg

Project Milestones – New Bed Tower:

  • Wound Care Renovations

  • CEP Equipment Removal

  • Construct Temporary Waldemere Garage Entrance

  • After Garage Entrance is complete construct Interim Main Entrance

  • Old Central Energy Plant Structure Demolition

  • Construct Temporary ECC Canopy & Drop off

  • Open Temporary Canopy & Drop Off / Close Hawthorne in Front of ECC / Construct New ECC Drop Off

  • Install New & Relocate Site Utilities / Construct New Loop Road

  • Open New Loop Road / New Drop Offs / Close Hawthorne / Capture Site for Bed Tower Demolition / Construct Stair & Elevator Tower & Bridge Connector

  • New Bed Tower Construction

Target Completion - 7/1/10

Target Start - 3/8/10

Target Start - 3/29/10

Target Start - 5/17/10

Target Start - 3/29/10

Target Start - 5/3/10

Target - 6/7/10

Target Start - 5/3/10

Target Start - 9/20/10

Target Start - 12/28/10


Site phasing diagram 1 l.jpg

Site Phasing Diagram - 1

Create Temporary Garage Entry/Exit onto Waldemere St

Remove Equipment from CEP

Demolish Old CEP

Interim Moves for Surgery Support & Pathology


Site phasing diagram 2 l.jpg

Site Phasing Diagram - 2

Create Temporary ECC Entry Drop-Off

Temporary ECC Entry Canopy


Site phasing diagram 3 l.jpg

Site Phasing Diagram - 3

Open New Entry/Exit at Waldemere Garage

Build Temp Main Entrance Canopy, Drop-off & Vestibule

Construct New Loop Road and Associated Utilities

Close Hawthorne Street

Open Temporary ECC Entry Canopy & Drop-off

Construct New ECC Vestibule, Canopy & Drop-off

Temporary Route to ECC


Site phasing diagram 4 l.jpg

Site Phasing Diagram - 4

Open New Loop Road

Open Temporary Main Entry Canopy & Drop-off

Open ECC Vestibule, Canopy & Drop-off

Demolish Existing Main Entry Canopy

Demolish Portion of Critical Care Tower for New Bridge

Demolish Northeast Tower


Site phasing diagram 5 l.jpg

Site Phasing Diagram - 5

Construct New Bed Tower and Bridge


ad